PRB Meeting Date: 2/28/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/1/2023 3:13:57 PM Olivier Mirza , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W OF SALOME RD - W OF TONOPAH PAVEMENT REHABILITATION OR1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 10 Maricopa 80.0 F058301D 10.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,859,000 17. Original Program Item #: 103121
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,859,000 ($1,345,000) (0%) $514,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1754 Item #:103121 (NHPP ) FY:0 FundSRC: Desc: $ -1859 Item #:72523 ( ) FY:2023 FundSRC:. Desc:PRESERVATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project.
26. JUSTIFICATION
As per the completed Pavement Management performance measures, the existing pavement has experienced distress cracking and is in substandard condition. The project will rehabilitate the existing pavement as recommended in the Planning Level Pre-scoping document. The design of this project is programmed in FY23 with construction programmed in FY25. Staff: $363K Consultant: $102K ICAP: $49K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.