PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 6/4/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2024 8:28:11 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MAIN ST; HWY 70 - 1200 S | ROADWAY WIDENING AND DRAINAGE | OQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 0000 | Graham | PIM | T056003D | 1.46 |
16. Original Program Budget: $338,000 | 17. Original Program Item #: 140390 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$338,000 | $0 (0%) | $338,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009662-I |
$ 338 Item #:73424 (100pct AZSMART FUNDS) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
This is a Town of Pima Project with AZSMART grant awarded to address congestion and safety concerns by widening the road, adding turn lanes, bike lanes and sidewalks. This is a consultant design project. Consultant : $338k ($337,760) TIP ID: PMA24-01 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 6/4/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2024 8:27:30 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MAIN ST; HWY 70 - 1200 S | ROADWAY WIDENING AND DRAINAGE | OQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 0000 | Graham | PIM | T056001D | 1.46 |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 140390 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 24-0009662-I |
$ 30 Item #:73424 (100pct AZSMART FUNDS) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
This is an AZSMART funded project to the Town of Pima to address congestion and safety concerns by widening the road, adding turn lanes, bike lanes and sidewalks. This is a consultant design project. Staff: $30k TIP ID: PMA24-01 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 10/17/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/11/2024 2:19:37 PM | Lisa Danka | (602) 712-4675 | 1611 W Jackson St, , 200B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Main Street, US70 - 1200 S. | WIDEN ST, ADD TURN LANE, BIKE LANES & SIDEWALKS | OQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | Graham | T056001D | 1.46 |
16. Original Program Budget: $0 | 17. Original Program Item #: |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $0 (0%) | $0 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
FYI only. |
26. JUSTIFICATION |
This is an AZ SMART Fund application from the Town of Pima for design and other engineering services (DOES) to plan and design the widening of Main Street, adding a turn lane, bike lanes and sidewalks. The Town intends to apply for the Federal Rural Surface Transportation Grant for construction funding in the 2025 round. See attached AZ SMART application. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
FYI/Guidance. | Subject to PPAC Approval. |
Arizona Department of Transportation |