PRB Meeting Date: 6/4/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2024 8:28:11 AM Chinwe Iwuchukwu (626) 222-7982 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MAIN ST; HWY 70 - 1200 S ROADWAY WIDENING AND DRAINAGE OQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Graham PIM T056003D 1.46  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $338,000 17. Original Program Item #: 140390
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$338,000 $0 (0%) $338,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 24-0009662-I
$ 338 Item #:73424 (100pct AZSMART FUNDS) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is a Town of Pima Project with AZSMART grant awarded to address congestion and safety concerns by widening the road, adding turn lanes, bike lanes and sidewalks. This is a consultant design project. Consultant : $338k ($337,760) TIP ID: PMA24-01
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 6/4/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2024 8:27:30 AM Chinwe Iwuchukwu (626) 222-7982 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MAIN ST; HWY 70 - 1200 S ROADWAY WIDENING AND DRAINAGE OQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Graham PIM T056001D 1.46  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $30,000 17. Original Program Item #: 140390
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$30,000 $0 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 24-0009662-I
$ 30 Item #:73424 (100pct AZSMART FUNDS) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is an AZSMART funded project to the Town of Pima to address congestion and safety concerns by widening the road, adding turn lanes, bike lanes and sidewalks. This is a consultant design project. Staff: $30k TIP ID: PMA24-01
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 10/17/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/11/2024 2:19:37 PM Lisa Danka (602) 712-4675 1611 W Jackson St, , 200B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Main Street, US70 - 1200 S. WIDEN ST, ADD TURN LANE, BIKE LANES & SIDEWALKS OQ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford Graham T056001D 1.46  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $0 (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
 

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
FYI only.
26. JUSTIFICATION
This is an AZ SMART Fund application from the Town of Pima for design and other engineering services (DOES) to plan and design the widening of Main Street, adding a turn lane, bike lanes and sidewalks. The Town intends to apply for the Federal Rural Surface Transportation Grant for construction funding in the 2025 round. See attached AZ SMART application.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
FYI/Guidance. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox