PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 3/26/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/28/2024 9:26:23 AM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR87 AND KLECK RD | CONSTRUCT LEFT TURN LANES | OQ1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 87 | Pinal | 127.8 | F055301D | 0.1 | 087-A(215)T |
16. Original Program Budget: $255,000 | 17. Original Program Item #: 101747 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$255,000 | $24,000 (0%) | $279,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 240 Item #:101747 (94.3pct Federal HSIP) FY:0 FundSRC: Desc: | $ 23 Item #:70124 (94.3pct Federal HSIP) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget. |
26. JUSTIFICATION |
This is an HSIP project to construct left turn lanes on SR87 at each approach of the Kleck Road intersection. Budget increase needed for cultural monitoring and flagging cost required for a cultural site found along the SE corner of SR87 and Kleck intersection. Consultant $19K ICAP $5K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 3/12/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/14/2024 8:54:53 AM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR87 AND KLECK RD | CONSTRUCT LEFT TURN LANES | OQ1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 87 | Pinal | 127.8 | F055301C | 0.1 | HSIP087-A(215)T |
16. Original Program Budget: $950,000 | 17. Original Program Item #: 101747 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$950,000 | $525,000 (0%) | $1,475,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 895 Item #:101747 (94.3pct Federal HSIP ($895,850.00)) FY:0 FundSRC: Desc: | $ 495 Item #:70124 (94.3pct Federal HSIP) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 3/21/2024 | 23a. Bid Adv Date: | 4/24/2024 |
25. DESCRIPTION OF REQUEST |
Increase budget. Change schedule from 3rd to 4th Quarter. |
26. JUSTIFICATION |
This is an HSIP project to construct left turn lanes on SR87 at each approach of the Kleck Road intersection. Construction is scheduled for FY24. The Stage IV estimate came in higher than the programmed budget due to increase in unit prices of AC, AB and roadway excavation costs. There was also a quantity increase in roadway excavation and guardrail. ICAP is included in this request. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Schedule. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 10/18/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/20/2022 2:26:51 PM | Angela Galietti | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR87 AND KLECK RD | CONSTRUCT LEFT TURN LANES | OQ1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 87 | Pinal | 127.8 | F055301D | 0.1 | 087-A(215)T |
16. Original Program Budget: $255,000 | 17. Original Program Item #: 101747 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$255,000 | $0 (0%) | $255,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 240 Item #:101747 (94.3pct Federal HSIP) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
This is an HSIP project to construct left turn lanes on SR87 at each approach of the Kleck Road intersection. Construction is scheduled for FY24. Staff: $168K Consultant: $62K ICAP: $24K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |