PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/5/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/18/2024 2:47:21 PM Kirstin Huston (602) 712-2167 205 S 17th Ave, , 121F
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 202 RED MOUNTAIN - SR 202 SANTAN PAVEMENT REHABILITATION OP1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 101L Maricopa 51.5 F073501X 10  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104442
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $13,612,000 (0%) $13,612,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 13612 Item #:49924 ( 100 pct RARF - MAG TIP ID DOT24-224) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 24  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
Pavement rehabilitation project on SR 101 from SR 202 Red Mountain to SR 202 Santan, consisting of diamond grinding as part of the Maricopa Association of Governments (MAG) expansion of the Diamond Grind Pilot Program. Project will use a procurement contract. Funds approved at MAG Regional Council on February 28, 2024.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation