PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 5/16/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/18/2023 8:26:06 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WALNUT CREEK - HOLY MOSES WASH | PAVEMENT REHABILITATION | ON1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 33.0 | F039201D | 13.2 | NHPP040-A(383)T |
16. Original Program Budget: $460,000 | 17. Original Program Item #: 101683 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$460,000 | $22,000 (0%) | $482,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 460 Item #:101683 ( ) FY:0 FundSRC: Desc: | $ 22 Item #:72323 (.) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
The subject project has advertised for construction and bids have been opened. The additional funds are needed to cover the payroll and ICAP rejects and to take the project through to the award. Staff - $20k ICAP - $2K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 12/20/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/22/2022 11:02:02 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WALNUT CREEK - HOLY MOSES WASH | PAVEMENT REHABILITATION | ON1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 33.0 | F039201C | 13.2 | NHPP040-A(383)T |
16. Original Program Budget: $35,835,000 | 17. Original Program Item #: 101683 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$35,835,000 | $2,665,000 (0%) | $38,500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 35835 Item #:101683 ( ) FY:0 FundSRC: Desc: | $ -35835 Item #:100832-24 (.) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 24 | 21a. Fiscal Year: | 23 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: | 2/20/2023 |
25. DESCRIPTION OF REQUEST |
Advance Project to FY23 |
26. JUSTIFICATION |
The project was originally programmed in FY23. The project was deferred to FY24 since more time was needed to secure clearances and complete the design. It was the intent of the Department to bring this project back into FY23 when design was complete and funding became available. ICAP is included in the request. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 7/26/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
7/28/2022 9:22:44 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WALNUT CREEK - HOLY MOSES WASH | PAVEMENT REHABILITATION | ON1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 33.0 | F039201C | 13.2 | NHPP040-A(383)T |
16. Original Program Budget: $35,835,000 | 17. Original Program Item #: 101683 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$35,835,000 | ($35,835,000) (0%) | $0 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 28000 Item #:101683 ( ) FY:0 FundSRC: Desc: | $ -35835 Item #:72523 (.) FY:2023 FundSRC:. Desc:PRESERVATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 23 | 21a. Fiscal Year: | 24 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 1/17/2023 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer Project to FY24 |
26. JUSTIFICATION |
Defer project to FY24. Funding to be used to advance an FY24 project that is ready to advertise. It is the intent of the Department to bring this project back into FY23 when funding becomes available. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 9:20:11 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
WALNUT CREEK - HOLY MOSES WASH | PAVEMENT REHABILITATION | ON1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 40 | Mohave | 33.0 | F039201D | 13.2 | 040-A(383)T |
16. Original Program Budget: $427,000 | 17. Original Program Item #: 101683 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$427,000 | $33,000 (0%) | $460,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 476 Item #:101683 ( ) FY:0 FundSRC: Desc: | $ 33 Item #:72521 (Based on DICE ) FY:2021 FundSRC:. Desc:PRESERVATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Project |
26. JUSTIFICATION |
This project will perform pavement rehabilitation along WB & EB I-40 for 13 miles from Walnut Creek to Holy Moses Wash. This project also includes deck repair with PPC overlay, guardrail replacement, installing flared end sections at CMP crossings, and TCB for traffic control. Staff: $395K Consultant: $33K ICAP: $48K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 4/20/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2021 9:21:29 AM | Michael Andazola | (602) 712-7629 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Walnut Creek to Holy Moses Wash | Pavement Rehabilitation | ON1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Prescott | 40 | Mohave | 33 | F039201C | 13.2 | 040-A(383)T |
16. Original Program Budget: $28,000,000 | 17. Original Program Item #: 101683 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$28,000,000 | $7,835,000 (0%) | $35,835,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 28000 Item #:101683 ( ) FY:0 FundSRC: Desc: | $ 7835 Item #:72523 (.) FY:2023 FundSRC:. Desc:PRESERVATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 23 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
The estimate used for programming was prepared in 2017 and did not include contingency for unidentified items and cost for the year of expenditure. The updated construction estimate for the year of expenditure includes contingency for unidentified items and cost for the year of expenditure. ICAP is included in this request. Contingent upon PPAC approval, this will be included in the FY22-FY26 Five Year Program. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |