PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 2/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/13/2025 8:40:43 AM Chris Moore (757) 469-6679 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN SIMON PORT OF ENTRY REPLACE SCALE & CONSTRUCT INSPECTION PIT OI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 383.0 F072801C 0.3 010-F(238)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,800,000 17. Original Program Item #: 104462
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,800,000 $0 (0%) $4,800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4800 Item #:104462 ( ) FY:0 FundSRC: Desc: $ -4800 Item #:72325 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 28  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer project.
26. JUSTIFICATION
This project will replace the scale and construct two enclosed inspection pits at the San Simon Port of Entry. Improvements include replacing the well, ADA walkways, median removal, secured employee parking, an access gate from the Frontage Road, pavement markings, and utility service adjustments. Request to move scheduled advertisement to FY28 due to change in funding priority.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/10/2024 9:48:36 AM Chris Moore (757) 469-6679 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN SIMON PORT OF ENTRY REPLACE SCALE & CONSTRUCT INSPECTION PIT OI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 383.0 F072801C 0.3 010-F(238)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,800,000 17. Original Program Item #: 104462
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,800,000 ($4,800,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4800 Item #:104462 ( ) FY:0 FundSRC: Desc: $ -4800 Item #:72325 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer project.
26. JUSTIFICATION
This project will replace the scale and construct two enclosed inspection pits at the San Simon Port of Entry. Improvements include replacing the well, ADA walkways, median removal, secured employee parking, an access gate from the Frontage Road, pavement markings, and utility service adjustments. Request to move scheduled advertisement to FY27.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Request Withdrawn.


PRB Meeting Date: 8/20/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/6/2024 2:51:56 PM Chris Moore (757) 469-6679 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN SIMON PORT OF ENTRY REPLACE SCALE & CONSTRUCT INSPECTION PIT OI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 383.0 F072801D 0.3 010-F(238)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $634,000 17. Original Program Item #: 104462
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$634,000 $482,000 (0%) $1,116,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 634 Item #:104462 ( ) FY:0 FundSRC: Desc: $ 482 Item #:74325 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change scope. Increase budget.
26. JUSTIFICATION
The project scope of work will add a second inspection pit adjacent to the first pit with one enclosed building for both pits, a new credential booth connected to the scale foundation, and replacement of the well at the San Simon Port of Entry. New scope items have increased the budget. Staff $5k Consultant $442k ICAP $35k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 3/26/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/28/2024 9:25:51 AM Chris Moore (757) 469-6679 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN SIMON PORT OF ENTRY REPLACE SCALE & CONSTRUCT INSPECTION PIT OI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 383.0 F072801D 0.3 010-F(238)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104399
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $634,000 (0%) $634,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 634 Item #:74324 ( ) FY:2024 FundSRC:. Desc:PORT OF ENTRY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will replace the scale and construct an inspection pit at the San Simon Port of Entry to improve vehicle enforcement operations. Improvements include concrete pavement, ADA walkways, median removal, secured employee parking, an access gate from the Frontage Road, pavement markings, and utility service adjustments. Construction is anticipated in FY25. Staff $61k Consultant $512k ICAP $61k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation