PRB Meeting Date: 3/26/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/28/2024 9:25:51 AM Chris Moore (757) 469-6679 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SAN SIMON PORT OF ENTRY REPLACE SCALE & CONSTRUCT INSPECTION PIT OI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 383.0 F072801D 0.3 010-F(238)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104399
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $634,000 (0%) $634,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 634 Item #:74324 ( ) FY:2024 FundSRC:. Desc:PORT OF ENTRY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
This project will replace the scale and construct an inspection pit at the San Simon Port of Entry to improve vehicle enforcement operations. Improvements include concrete pavement, ADA walkways, median removal, secured employee parking, an access gate from the Frontage Road, pavement markings, and utility service adjustments. Construction is anticipated in FY25. Staff $61k Consultant $512k ICAP $61k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.