PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/18/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/21/2024 9:22:31 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SENECA LAKE TRAILS & RECREATIONAL SITE IMPROVEMENT INFRASTRUCTURE IMPROVEMENTS OC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Gila ISC T055401D 0.0 ISC-0(204)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $276,000 17. Original Program Item #: 104269
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$276,000 $0 (0%) $276,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 276 Item #:71624 ($275,486 Transportation Alternatives) FY:2024 FundSRC:. Desc:TRANSPORTATION ALTERNATIVES $ -276 Item #:71624 ($275,486 Transportation Alternatives) FY:2024 FundSRC:. Desc:TRANSPORTATION ALTERNATIVES  

Current Approved New Project/Change Request  
21. Fiscal Year: 24 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change in schedule.
26. JUSTIFICATION
The San Carlos Apache Tribe has elected to administer this project and are coordinating with the Bureau of Indian Affairs to receive the funds via a pass through. This project is funded by the Transportation Alternatives program and is programmed in Fiscal Year 24. The project needs to be moved Fiscal Year 25 to allow the San Carlos Apache Tribe to continue coordinating with BIA and the TA funding being available in FY25 to transfer to BIA.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation