PRB Meeting Date: 10/21/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/23/2025 12:00:58 PM Alyssa Young (480) 932-9468 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
EAST WETLAND PARK - PACIFIC AVE SHARED-USE PATHWAY NV1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 0000 Yuma YUM T054501C 0.0 CRP YUM-0(229)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $302,000 17. Original Program Item #: 104182
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$302,000 $0 (0%) $302,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 0009594
$ 302 Item #:104182 ( Fed $284,156 Local $17,176) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 12/18/2025 23a. Bid Adv Date: 3/13/2026

25. DESCRIPTION OF REQUEST
Move Advertisement Quarter.
26. JUSTIFICATION
The project is experiencing delays with environmental clearance and additional documents, related to Bureau of Reclamation`s involvement on the project. A meeting with the BOR was cancelled due to the government shut down, with no clear indication of a timeframe when they will be able to meet again. The BOR is a landowner and rights user for a section of the project that we are encroaching. The coordination and finalization of paperwork with the BOR is necessary to move forward with stage IV submittal, which is currently TBD with the shutdown. Requesting to move advertisement from December 2025 to March 2026, this will allow us ample time to handle the BOR situation, submit stage IV documents and move forward with all typical project related reviews.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Schedule. Item(s) Approved.