PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 10/25/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/28/2022 10:17:25 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
BULLHEAD PARKWAY & SILVER CREEK ROAD | INSTALL LIGHTING & SIGNING | NR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Mohave | BUL | T027801C | 0.0 | HSIPBUL-0(204)T |
16. Original Program Budget: $747,000 | 17. Original Program Item #: 100501 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$747,000 | $255,000 (0%) | $1,002,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 20-0007979-I |
$ 139 Item #:OTHR23 (City contribution @ 100pct = $139,222) FY:0 FundSRC: Desc: | $ 255 Item #:70123 (The amount is 100pct Federal-Aid (HSIP) ) FY:2023 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 23 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
The scope of the project includes, installation of street lighting, chevrons, curve warning signs, speed feedback signs, stop ahead and larger stop signs, signal ahead signs and replacement of traffic signal backplates with reflective backplates. The project has been determined to be eligible for additional HSIP funds to cover the difference between the Department`s authorized estimate and contractor`s bid amount. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. | Request Withdrawn. |
PRB Meeting Date: 6/21/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/22/2022 2:33:06 PM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
BULLHEAD PARKWAY & SILVER CREEK ROAD | INSTALL LIGHTING & SIGNING | NR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Mohave | BUL | T027801C | 0.0 | HSIPBUL-0(204)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 100501 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $747,000 (0%) | $747,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 20-0007979-I |
$ 608 Item #:70123 (The amount is 100pct Federal-Aid (HSIP) ) FY:2023 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 23 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Construction Project |
26. JUSTIFICATION |
The scope of the project includes, installation of street lighting, chevrons, curve warning signs, speed feedback signs, stop ahead and larger stop signs, signal ahead signs and replacement of traffic signal backplates with reflective backplates. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. Project is included in new Five Year Program. |
PRB Meeting Date: 4/26/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/23/2023 8:46:56 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
BULLHEAD PARKWAY & SILVER CREEK ROAD | INSTALL LIGHTING & SIGNING | NR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Mohave | BUL | T027801C | 0.0 | HSIPBUL-0(204)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 100501 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $747,000 (0%) | $747,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 20-0007979-I |
$ 139 Item #:OTHR22 (City contribution @ 100pct = $139,222) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 22 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: | 6/10/2022 |
25. DESCRIPTION OF REQUEST |
Establish Construction Project |
26. JUSTIFICATION |
The scope of the project includes, installation of street lighting, chevrons, curve warning signs, speed feedback signs, stop ahead and larger stop signs, signal ahead signs and replacement of traffic signal backplates with reflective backplates. There have been fatal and incapacitating injury crashes within these roadway segments. These improvements will directly address to reduce these types of crashes and thus improving the safety. Contingent upon receiving local funds, prior to PPAC. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/19/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/19/2022 9:31:09 AM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
BULLHEAD PARKWAY & SILVER CREEK ROAD | INSTALL LIGHTING & SIGNING | NR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Mohave | BUL | T027801C | 0.0 | HSIPBUL-0(204)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 100501 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $608,000 (0%) | $608,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 20-0007979-I |
$ 608 Item #:70122 (The amount is 100pct Federal-Aid (HSIP) ) FY:2022 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 22 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: | 6/10/2022 |
25. DESCRIPTION OF REQUEST |
Establish Construction Project |
26. JUSTIFICATION |
The scope of the project includes, installation of street lighting, chevrons, curve warning signs, speed feedback signs, stop ahead and larger stop signs, signal ahead signs and replacement of traffic signal backplates with reflective backplates. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 2/23/2021 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/24/2021 4:29:02 PM | Bharat Kandel | (602) 712-8736 | 205 S 17th Ave, , EM01 |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
BULLHEAD PARKWAY & SILVER CREEK ROAD | INSTALL LIGHTING & SIGNING | NR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 0000 | Mohave | BUL | T027801D | 0.0 | HSIPBUL-0(204)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 100501 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $361,000 (0%) | $361,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 20-0007979-I |
$ 361 Item #:70121 ( ) FY:2021 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Design Project |
26. JUSTIFICATION |
The Intergovernmental Agreement of the subject HSIP project has been executed. The project consists of roadway lighting, dynamic speed feedback signs, chevrons and curve warning signs, advance Stop Ahead and Signal Ahead Signs, larger STOP signs, and replacement of traffic signal backplates on Bullhead Parkway from Canyon Road to Hillview Drive. The project includes installation of streetlight, chevrons, curve warning signs, and speed feedback signs on Silver Creek Road from SR95 to Bullhead Parkway. Consultant - $331k ADOT PDA Fee - $30k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |