PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/7/2022 9:52:17 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROW Acquisition NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901R 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,000,000 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,000,000 ($500,000) (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 500 Item #:79921 ( ) FY:0 FundSRC: Desc: $ -500 Item #:102079 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Correct Programming Error
26. JUSTIFICATION
The FY21 approved budget is sufficient for ROW acquisition. An inadvertent duplication of funds was placed in FY22 and the duplication did not decrease funds from the $28M GF allocation for the US 95 roadway segment. There is no funding to decrease from the project. This action deletes the entry error.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2022 1:55:29 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROADWAY WIDENING NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901C 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $6,536,000 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$6,536,000 $22,364,000 (0%) $28,900,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 22-8488
$ 3286 Item #:79921 ( ) FY:0 FundSRC: Desc: $ 12364 Item #:72322 (.) FY:2022 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 22 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 5/20/2022 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/20/2022 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
This project was underfunded when it was established. The additional funding will allow construction of the entire 3+ miles of widening plus replacement of the Wellton-Mohawk Canal Bridge. ICAP is included in the request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/6/2022 1:55:09 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROADWAY WIDENING NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901D 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,450,000 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,450,000 $733,000 (0%) $3,183,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #:73321 ( ) FY:2021 FundSRC:. Desc:STATEWIDE MINOR PROJECTS $ 124 Item #:77722 (Environmental) FY:2022 FundSRC:. Desc:ENVIRONMENTAL SUPPORT SERVICES  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
The original scope was approved based upon the use of 30pct plans previously prepared by ADOT in 2011. Out of scope work was requested by ADOT and additional effort beyond that in the approved scope is required in the following areas: Environmental: - Ethnographic study for US 95 roadway to mitigate adverse effects related to the historical significance of the route. - Additional consultation and review submittals of CE and cultural documents. Engineering: - WMIDD Siphon - Originally proposed to be extended in place; two alternatives were prepared requiring extensive research and coordination with Wellton Mohawk Irrigation district. Ultimately construction drawings and details will be prepared for full replacement of the siphon in a relocated crossing of US 95. - Extensive design refinements to minimize ROW needs and UPRR impacts. Avoided time-consuming effort with UPRR by redesigning features adjacent to the RR ROW. -Extensive out of scope hydrologic evaluation and alternatives comparison resulting in re-design and adding numerous culvert crossings to mitigate RR ROW and roadway flooding. Admin: - Discovery of above additional items required additional administrative time and meetings. Staff: $50K Consultant: $612K ICAP: $71K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/5/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/5/2022 9:20:17 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK Utility Relocation NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901U 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,000,000 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,000,000 ($500,000) (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 500 Item #:79921 ( ) FY:0 FundSRC: Desc: $ -500 Item #:102079 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Correct Programming Error
26. JUSTIFICATION
The FY21 approved budget is sufficient for Utility relocations. An inadvertent duplication of funds was placed in FY22 and the duplication did not decrease funds from the $28M GF allocation for the US 95 roadway segment. There is no funding to decrease from the project. This action deletes the entry error.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 4/27/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 10:29:43 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK Utility Relocation NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901U 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $500,000 (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 500 Item #:79921 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Subphase
26. JUSTIFICATION
Widening the roadway from two to five lanes will require relocation of prior rights utilities. This subphase will fund Utility relocation agreements needed for the widening. Utility Relocations: $455K ICAP: $45K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/27/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 10:29:56 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROW Acquisition NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901R 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $500,000 (0%) $500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 500 Item #:79921 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Subphase
26. JUSTIFICATION
Widening the roadway from two to five lanes will require new ROW and TCE acquisitions. This subphase will fund these acquisitions. ROW Acquisition: $455K ICAP: $45K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/27/2021
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2021 10:30:18 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROADWAY WIDENING NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901C 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $7,651,000 (0%) $7,651,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4401 Item #:79921 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will widen the existing 2-lane roadway to 5-lanes, with 2 lanes in each direction plus a continuous center turn lane. The scope will include culvert extensions and one bridge replacement (Wellton-Mohawk Canal Bridge) along with the widening. ICAP is included in the request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/22/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/23/2020 2:49:33 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE RD - WELLTON-MOHAWK ROADWAY WIDENING NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901D 3 095-B(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 102079
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $2,450,000 (0%) $2,450,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #:73321 (SW District Minor Projects Development funds) FY:2021 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will widen the existing 2-lane roadway to 5-lanes, with 2 lanes in each direction plus a continuous center turn lane. The scope will include culvert extensions and one bridge replacement (Wellton-Mohawk Canal Bridge). Survey/Mapping, ROW acquisition and pavement design to be completed by ADOT staff. Staff: $200K Consultant: $2,029K ICAP: $221K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/15/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/15/2020 9:49:05 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIFLE RANGE - WELLTON-MOHAWK ROADWAY WIDENING NM1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 95 Yuma 34.5 F035901D 3  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $2,400,000 (0%) $2,400,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #:73321 (SW District Minor Projects Development funds) FY:2021 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will widen the existing 2-lane roadway to 5-lanes, with 2 lanes in each direction plus a continuous center turn lane. The scope will include culvert extensions and one bridge replacement (Wellton-Mohawk Canal Bridge). Survey/Mapping, ROW acquisition and pavement design to be completed by ADOT staff. Staff: $200K Consultant: 1,984K ICAP: $216K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.