PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 5/19/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/26/2026 10:26:13 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| THORNTON RD; SR 84 - PETERS RD | WIDEN ROADWAY | NG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T053001C | 1.0 | CDS CSG-0(214)T |
| 16. Original Program Budget: $4,970,000 | 17. Original Program Item #: 104384 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $4,970,000 | $0 (0%) | $4,970,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 3000 Item #:90000 (Federal Earmark 94.3pct ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 26 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | 5/29/2026 | ||
| 25. DESCRIPTION OF REQUEST |
| Establish Construction Project. |
| 26. JUSTIFICATION |
| The work proposed for this project involves the constructing of an additional northbound thru lane on Thornton Road from SR 84 to Peters Road, reconstructing the southern portion of the road and installing new curb and gutter along with raised medians, widening the north portion of the road, installing new lighting along the southern portion of the road, minor drainage improvements, signing, pavement marking and other related work. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 4/28/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/30/2026 10:37:53 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| THORNTON RD; SR 84 - PETERS RD | WIDEN ROADWAY | NG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T053001C | 1.0 | CDS CSG-0(214)T |
| 16. Original Program Budget: $4,970,000 | 17. Original Program Item #: 104384 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $4,970,000 | $0 (0%) | $4,970,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 3000 Item #:90000 (Federal Earmark 94.3pct ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 26 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | 5/29/2026 | ||
| 25. DESCRIPTION OF REQUEST |
| Establish Construction Project. |
| 26. JUSTIFICATION |
| The work proposed for this project involves the constructing of an additional northbound thru lane on Thornton Road from SR 84 to Peters Road, reconstructing the southern portion of the road and installing new curb and gutter along with raised mediuns, widening the north portion of the road, installing new lighting along the southern portion of the road, minor drainage improvements, signing, pavement marking and other related work. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. Change in Schedule. | Request Withdrawn. |
| PRB Meeting Date: 1/28/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/30/2025 8:46:19 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| THORNTON RD; SR 84 - PETERS RD | WIDEN ROADWAY | NG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T053001C | 1.0 | CDS CSG-0(214)T |
| 16. Original Program Budget: $5,000,000 | 17. Original Program Item #: 104384 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $5,000,000 | $0 (0%) | $5,000,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 3000 Item #:104384 (Federal Earmark 94.3pct ) FY:0 FundSRC: Desc: | $ -3000 Item #:104384 (Federal Earmark 94.3pct ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 25 | 21a. Fiscal Year: | 26 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 1/7/2025 | 23a. Bid Adv Date: | 12/17/2025 | |
| 25. DESCRIPTION OF REQUEST |
| Defer to FY26 |
| 26. JUSTIFICATION |
| Based on the baseline schedule established after the kickoff meeting, the project will be advertised for construction in December 2025. The Environmental Clearance schedule target is July 17, 2025. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. Change in Schedule. | Item(s) Approved. |
| PRB Meeting Date: 10/22/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/25/2024 9:34:17 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| THORNTON RD; SR 84 - PETERS RD | WIDEN ROADWAY | NG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T053001D | 1.0 | CDS CSG-0(214)T |
| 16. Original Program Budget: $30,000 | 17. Original Program Item #: 104384 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $30,000 | $0 (0%) | $30,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 30 Item #:OTHR25 (100PCT LOCAL FUNDS) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project |
| 26. JUSTIFICATION |
| Widening the roadway to two (2) lanes in each direction on Thornton Road; SR84 - Peters Rd. This is a CDS funded project. Staff $30K TIP Year Project ID: CSG 23-04 |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 8/27/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 8/29/2024 8:35:53 AM | Chinwe Iwuchukwu | (626) 222-7982 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| THORNTON RD; SR 84 - PETERS RD | WIDEN ROADWAY | NG1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Tucson | 0000 | Pinal | CSG | T053001D | 1.0 | CDS CSG-0(214)T |
| 16. Original Program Budget: $30,000 | 17. Original Program Item #: 104384 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $30,000 | $0 (0%) | $30,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 24-0009573-I |
| $ 30 Item #:OTHR25 (100PCT LOCAL FUNDS) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project |
| 26. JUSTIFICATION |
| Widening the roadway to two (2) lanes in each direction on Thornton road; SR84 - Peters Rd. This is a CDS funded project. Staff $30K TIP Year Project ID: CSG 23-04 |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |