PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 3/19/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/20/2024 7:19:41 AM | Judah Cain | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MOON CANYON BRIDGE #10538 | BRIDGE REHABILITATION | MW1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
0000 | Cochise | BIS | T052403D | 0.0 | OSB BIS-0(205)T |
16. Original Program Budget: $500,000 | 17. Original Program Item #: 103800 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$500,000 | $0 (0%) | $500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009557-I |
$ 500 Item #:103800 (Off System Bridge) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project. |
26. JUSTIFICATION |
This bridge rehabilitation project will strengthen the existing bridge deck to increase load carry capacity, install new concrete barriers and curbs, repair abutment/retaining walls and add scour protection to the abutments and channel bottom. This is an Off-system Bridge Project. Consultant: $500K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 3/19/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/22/2024 3:10:09 PM | Judah Cain | , , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
MOON CANYON BRIDGE #10538 | BRIDGE REHABILITATION | MW1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
0000 | Cochise | BIS | T052401D | 0.0 | OSB BIS-0(205)T |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 103800 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009557-I |
$ 30 Item #:103800 (Off System Bridge ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project. |
26. JUSTIFICATION |
This bridge rehabilitation project will strengthen the existing bridge deck to increase load carry capacity, install new concrete barriers and curbs, repair abutment/retaining walls and add scour protection to the abutments and channel bottom. This is an Off-system Bridge Project Staff: $30K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |