PRB Meeting Date: 11/10/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/9/2026 11:14:31 AM Annette Riley (602) 712-4241 206 S 17TH AVE, 193, 139A
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 89A Emergency Repair MS1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 89A Yavapai 375 F097601C 22  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $25,000,000 (0%) $25,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 25000 Item #:72327 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 2027 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 11/30/2026 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 12/29/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Request to establish project. GEC and Staff Charges - $357K, ICAP - $23K Construction - $23M, ICAP - $1.5M
26. JUSTIFICATION
The roadway along SR-89A between approximately milepost 375 and 397 had above average rainfall causing significant damage to the roadway and drainage system including pavement damage, slope failure, guardrail damage, etc. This request will establish the project to restore/rebuild the damaged areas. We are pursuing ER funds.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.