MP 339 - I-40 CENTERLINE RUMBLE STRIPS MS1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 89 Yavapai 339.0 F051901D 24.0 HSIP089-B(220)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $129,000 17. Original Program Item #: 101699
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$129,000 $88,000 (0%) $217,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 129 Item #:101699 ( ) FY:0 FundSRC: Desc: $ -129 Item #:70123 (HSIP design) FY:2023 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project
26. JUSTIFICATION
This is a 100pct HSIP project to install centerline rumble strips. Project name/Location should be MP339 - I-40. Staff: $138K Consultant: $58K ICAP: $21K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.