PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 10/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/24/2023 12:41:38 PM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10, SR 202L - Gila River Bridge | Construction | MN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 10 | Maricopa | 161 | F027102C | 12 |
16. Original Program Budget: $0 | 17. Original Program Item #: 102489 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $7,807,000 (0%) | $7,807,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 7807 Item #:72324 (move funding to design phase.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 10/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/24/2023 12:38:21 PM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10, Wild Horse Pass TI | Construction | MN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 10 | Maricopa | 161 | F027102C | 1 |
16. Original Program Budget: $0 | 17. Original Program Item #: 104086 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $37,600,000 (0%) | $37,600,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 37600 Item #:72324 (move funding to design build phase.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. This action moves the construction funding from one of the elements of the project to the new project number. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 10/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/24/2023 12:38:32 PM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10, Riggs Rd - Gila River Bridge | Construction | MN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 10 | Maricopa | 161 | F027102C | 12 |
16. Original Program Budget: $0 | 17. Original Program Item #: 100789 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $150,400,000 (0%) | $150,400,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 150400 Item #:72324 (move funding to design build phase FY24 to FY25.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. This action moves the construction funding from one of the elements of the project to the new project number. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 10/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/24/2023 12:38:11 PM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10, Riggs Rd TI | Construction | MN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 10 | Maricopa | 161 | F027102C | 1 |
16. Original Program Budget: $0 | 17. Original Program Item #: 104082 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $33,000,000 (0%) | $33,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 33000 Item #:72324 (move funding to design build phase.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. This action moves the construction funding from one of the elements of the project to the new project number. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 10/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/24/2023 12:42:00 PM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
I-10, SR 202L (Santan) - Gila River Bridge | Construction | MN1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 10 | Maricopa | 161 | F027102C | 12 |
16. Original Program Budget: $0 | 17. Original Program Item #: 102489 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $693,000 (0%) | $693,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 693 Item #:72324 (move funding to design build project.) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
Arizona Department of Transportation |