PRB Meeting Date: 10/8/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/17/2024 8:09:21 AM Trent Kelso (602) 723-8313 205 S 17TH AVE, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
RIGGS RD - GILA RIVER CONSTRUCT FREEWAY WIDENING & CROSSROAD MM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 167.1 F072101C 6.3  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $150,400,000 17. Original Program Item #: 101860
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$150,400,000 ($8,614,000) (0%) $141,786,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 150400 Item #:101860 (HB2858) FY:0 FundSRC: Desc: $ -8614 Item #:DT55900 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease Budget Revise length
26. JUSTIFICATION
Funding is not needed and will be moved to F073401C. Request includes ICAP. Adjust length to 5.65 miles, to correspond with end of F072101C Design-Build project. This action is contingent upon MAG Regional Council Approval.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 6/4/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/4/2024 10:01:21 AM Carmelo Acevedo
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR202 (SANTAN) - GILA RIVER BRIDGE WIDEN ROADWAY MM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 161.0 F072101C 11.0 N/A
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: .
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $392,290,000 (0%) $392,290,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 179903 Item #:5723 (100pct RARF F0721 I-10 Design Build) FY:2020 FundSRC:. Desc:SR 202L (SANTAN) - RIGGS RD  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 2025  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Construction project
26. JUSTIFICATION
Construct roadway widening for new I-10 Design-Build project (Gila River Indian Community Project) from Loop 202 (Santan) to the Gila River Bridge. This request includes ICAP.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 5/7/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/7/2024 9:55:34 AM CARMELO ACEVEDO (480) 356-3535 206 S 17th Ave, , 304M
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
202L SANTAN - GILA RIVER BRIDGE WIDEN ROADWAY MM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 161 F072101C 11.8 010-C(222)S
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104187
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $392,407,000 (0%) $392,407,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 179903 Item #:5723 (100pct RARF) FY:2020 FundSRC:. Desc:SR 202L (SANTAN) - RIGGS RD  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Construction Project
26. JUSTIFICATION
Design and construction of I-10 from SR202L (MP161) to Riggs Rd (MP172.8).
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 10/24/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/24/2023 12:38:42 PM Carlos Lopez (602) 712-4786 206 S 17th Ave, 300, 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10, SR 202L (Santan) - Riggs Rd Construction MM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa 161 F027101C 12  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104187
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $179,902,000 (0%) $179,902,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 179902 Item #:49924 (move funding to design build project) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
The limits of the I-10 widening Design-Build project have now been identified and a new ADOT project number (F0721) has been established under which construction will be done. This action moves the construction funding from one of the elements of the project to the new project number.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.