PRB Meeting Date: 11/14/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/16/2023 9:52:33 AM Chinwe Iwuchukwu (626) 222-7982 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
OAK CREEK CANYON REPLACE GUARDRAIL MK1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff 89A Coconino 387.0 F071801D 3.0 A89-B(226)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104215
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $650,000 (0%) $650,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 650 Item #:73324 ( ) FY:2024 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This is a Minor Program Project to replace Guardrail to current MASH standards and the retaining wall on SR 89A within Coconino county. ADOT staff will perform compliance review, issue clearances and advertise the project for construction. Staff: $97K Consultant: $490K ICAP: $63K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox