PRB Meeting Date: 6/14/2022
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/16/2022 10:37:56 AM Lisa Danka (602) 712-4675 1611 W Jackson St, , 200B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
10: Sky Harbor West Airport Access Airport Access Improvements MC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 10 Maricopa _  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,500,000 17. Original Program Item #: 8884
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,500,000 $0 (0%) $2,500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2500 Item #: 8884 (RARF funds for predesign and env) FY:0 FundSRC: Desc: $ -2500 Item #:49922 (RARF funds for predesign and env) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 22 21a. Fiscal Year: 23  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Defer Project to FY23.
26. JUSTIFICATION
MAG Regional Council approved deferring the project for Pre-design and environmental to FY 23 on 5/25/22. No change was made for design, ROW or construction.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.