PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/26/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/1/2024 2:04:18 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| BIG JIM WASH | RECONSTRUCT TO A FOUR LANE DIVIDED HIGHWAY | LZ1O | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 93 | Yavapai | 161.7 | F073701D | 4.5 | NHPP |
| 16. Original Program Budget: $10,500,000 | 17. Original Program Item #: 8900 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $10,500,000 | $0 (0%) | $10,500,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 10500 Item #:8900 ( ) FY:0 FundSRC: Desc: | $ -10500 Item #:72725 (.) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 25 | 21a. Fiscal Year: | 24 | |
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Advance Design into FY24. |
| 26. JUSTIFICATION |
| This project will reconstruct to a four lane divided highway. Design project is currently in the Five Year Program in FY25. Staff $4,485K Consultant $5,000K ICAP $1,015K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in FY. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |