GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/1/2024 2:04:18 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
BIG JIM WASH RECONSTRUCT TO A FOUR LANE DIVIDED HIGHWAY LZ1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 93 Yavapai 161.7 F073701D 4.5 NHPP
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,500,000 17. Original Program Item #: 8900
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,500,000 $0 (0%) $10,500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10500 Item #:8900 ( ) FY:0 FundSRC: Desc: $ -10500 Item #:72725 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 24  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Advance Design into FY24.
26. JUSTIFICATION
This project will reconstruct to a four lane divided highway. Design project is currently in the Five Year Program in FY25. Staff $4,485K Consultant $5,000K ICAP $1,015K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Item(s) Approved. Subject to PPAC Approval.