PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 4/28/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/13/2026 7:19:00 PM | Chris Rodriguez | (602) 712-4642 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| WALNUT GROVE RD / WAGONER RD AT HASSAYAMPA RIVER | BRIDGE REHABILITATION | LY1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 0000 | Yavapai | YYV | T051001D | 0.2 | OSB YYV-0(217)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104446 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $45,000 (0%) | $45,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 25-0011419-I |
| $ 42 Item #:76426 (94.3pct OSB Funding $42,435.) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| This project is for rehabilitation of the existing Hassayampa River Bridge, Str. #08227. Contingent upon receipt of local funds prior to PPAC. ADOT Staff $45K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 4/28/2026 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/13/2026 7:19:25 PM | Chris Rodriguez | (602) 712-4642 | 205 S 17TH AVE, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| WALNUT GROVE RD / WAGONER RD AT HASSAYAMPA RIVER | BRIDGE REHABILITATION | LY1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Kingman | 0000 | Yavapai | YYV | T051003D | 0.2 | OSB YYV-0(217)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104446 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $400,000 (0%) | $400,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 25-0011419-I |
| $ 377 Item #:76426 (94.3pct OSB Funding $377,200) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project. |
| 26. JUSTIFICATION |
| This project is for rehabilitation of the existing Hassayampa River Bridge, Str. #08227. Contingent upon receipt of local funds prior to PPAC. Consultant $400K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 2/27/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/1/2024 2:05:38 PM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| WALNUT GROVE RD / WAGONER RD AT HASSAYAMPA RIVER | BRIDGE REHABILITATION | LY1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| 0000 | Yavapai | YYV | T051001L | 0.2 | OSB YYV-0(217)T | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: . |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $30,000 (0%) | $30,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009420-I |
| $ 2 Item #:OTHR24 (5.7pct. Local Match) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project |
| 26. JUSTIFICATION |
| Develop scoping and preliminary engineering documents for this Off System Bridge project for rehabilitation of the historical Hassayampa River Bridge (#8227). Staff $30K (Fed Funds $28,290 Local Match $1,710) |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 2/27/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/1/2024 2:05:56 PM | Chris Rodriguez | (602) 712-4642 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| WALNUT GROVE RD / WAGONER RD AT HASSAYAMPA RIVER | BRIDGE REHABILITATION | LY1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| 0000 | Yavapai | YYV | T051003L | 0.2 | OSB YYV-0(217)T | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: . |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $150,000 (0%) | $150,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009420-I |
| $ 9 Item #:OTHR24 (5.7pct. Local Match) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish New Project |
| 26. JUSTIFICATION |
| Develop scoping and preliminary engineering documents for this Off System Bridge project, for rehabilitation of the historical Hassayampa River Bridge (#8227). Consultant $150K (Fed Funds $141,450 Local Match $8,550). |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |