PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 9/22/2026
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/25/2026 9:54:49 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SW of Laguna Creek Emergency Relief Reconstruct Roadway LW1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 160 Apache 420 F097101X 1 160-B(213)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 106698
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $1,624,000 (0%) $1,624,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 500 Item #:72227 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
On September 16, 2026, significant monsoon rains in the vicinity of Dennehotso, AZ resulted in a 60+ foot long by 40 foot wide subsurface erosion that caused US 160 to collapse into the voice created by the eroded material. This has resulted in US 160 being closed in both directions at this location with a 250 mile round trip detour for the residents of the Dennehotso community. This request is for an emergency procurement contract to repair the erosion, install 2 - 36" corrugated metal pipes at the site of the erosion, repair the erosion damage, and repave the road, as well as for labor, equipment, and materials provided by ADOT during the initial response. The Declaration of Emergency is pending. Contractor: $1,430k Staff: $100k ICAP: $94k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation