PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 10/8/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/10/2024 8:50:25 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
GAS LINE RD - DIRK LAY RD | WIDEN ROADWAY | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 177 | F033601C | 4.5 | 010-C(227)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $160,593,000 (0%) | $160,593,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 59280 Item #:101838 (INFRA Grant - FG) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 2025 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Construction Project |
26. JUSTIFICATION |
Construct interstate widening from Gas Line Road to Dirk Lay Road, including reconstructing the Gas Line Rd bridge over I-10, constructing a new traffic interchange at Seed Farm Rd, and removing the Dirk Lay Rd bridge over I-10. This request includes ICAP. This action is contingent upon MAG Regional Council Approval. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 6/4/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/6/2024 8:48:56 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
GAS LINE RD - DIRK LAY ROAD | WIDEN ROADWAY | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601U | 6 | 010-C(227)T |
16. Original Program Budget: $3,500,000 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$3,500,000 | $7,000,000 (0%) | $10,500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3500 Item #:103007 (RIGGS TO SR 387 STATE 100PCT) FY:0 FundSRC: Desc: | $ 7000 Item #:101838 (From Item 104100 $7million F033601U) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
Additional Work includes relocation of Pima Maricopa Irrigation Project laterals crossing I-10 ROW as well as other lateral relocations, ditch relocations, and farm road reconnections related to Gila River Farms. The facilities are located between Gas Line and Seed Farm Rd. Utility Relocation $6,323k ICAP $677k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 6/4/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/4/2024 9:59:22 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
GAS LINE RD - DIRK LAY RD | WIDEN ROADWAY | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 177 | F033601C | 4.5 | 010-C(227)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $160,593,000 (0%) | $160,593,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 8200 Item #:101838 (Item 100771 SR 587 to SR 387, HB2858) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 2025 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish Construction Project |
26. JUSTIFICATION |
Construct interstate widening from Gas Line Road to Dirk Lay Road, including reconstructing the Gas Line Rd bridge over I-10, constructing a new traffic interchange at Seed Farm Rd, and removing the Dirk Lay Rd bridge over I-10. This request includes ICAP. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 5/7/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/21/2024 10:32:19 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - DIRK LAY ROAD | Utility Relocation | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 177 | F033601U | 4.5 | 010-C(227)T |
16. Original Program Budget: $3,500,000 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$3,500,000 | $7,500,000 (0%) | $11,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3500 Item #:103007 (I-10 Riggs to SR387 State 100pct) FY:0 FundSRC: Desc: | $ 7500 Item #:DT55900 (Laws 2022, Chapter 309 (HB 2858)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase Budget |
26. JUSTIFICATION |
Work includes relocation of Pima Maricopa Irrigation Project facilities between Seed Farm and Gas Line Rd. This request includes ICAP. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Request Withdrawn. |
PRB Meeting Date: 5/7/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/21/2024 10:32:29 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - DIRK LAY ROAD | WIDEN ROADWAY | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 177 | F033601C | 4.5 | 010-C(227)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $167,593,000 (0%) | $167,593,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 59280 Item #:90000 (I-10 INFRA Grant) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 2025 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
Construct interstate widening from N. of GasLine Road to Dirk Lay Road. This request includes ICAP. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 4/16/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/19/2024 2:13:25 PM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - DIRK LAY ROAD | WIDENING | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601D | 6 | 010-C(227)T |
16. Original Program Budget: $9,070,000 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$9,070,000 | $1,000,000 (0%) | $10,070,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5170 Item #:100965 ( ) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387 | $ 1000 Item #:103007 (I-10 Riggs to SR387 State 100pct ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget, Increase scope |
26. JUSTIFICATION |
Additional scope to include: Plant inventory, aesthetics design, Geotech Enviro. Clearance, environmental investigation and clearance for re-designed crossroads, design for culvert replacements, scoping memos and public outreach for Nelson Road and Casa Blanca layouts (changed from DCR), Pipe lining/MOT exhibits, FMS scoping and design, and CSRA prep/meeting. Consultant $853K Staff $50K ICAP $97K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Scope. | Item(s) Approved. |
PRB Meeting Date: 4/16/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/19/2024 2:39:41 PM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - DIRK LAY ROAD | WIDENING | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601U | 6 | 010-C(227)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $3,500,000 (0%) | $3,500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3500 Item #:103007 (I-10 Riggs to SR387 State 100pct) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new Subphase |
26. JUSTIFICATION |
Work includes relocation of utilities at the I-10 intersections of Seed Farm Rd, Gas Line Rd, Nelson Rd, and Casa Blanca Rd. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 1/24/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/26/2023 11:28:56 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - DIRK LAY ROAD | WIDENING | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601D | 6 | 010-C(227)T |
16. Original Program Budget: $4,770,000 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$4,770,000 | $4,300,000 (0%) | $9,070,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5170 Item #:100965 ( ) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387 | $ 4300 Item #:DT55900 (DT55900 I-10 Widening General Appropriation FY21) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget, Change beginning milepost, length and project name |
26. JUSTIFICATION |
Additional scope to incorporate initial and final design of Casa Blanca and Seed Farm interchanges with I-10 has been added. The added scope will include geotechnical investigation, roadway, structures, drainage, traffic control, signing, striping and erosion control. The consultant will also prepare all information necessary to obtain environmental clearance, ROW clearance, and utility clearance for the added work. Change beginning milepost to 173.75 and length of project to 7.74 miles. Change project name to "North of Nelson Rd. - Dirk Lay Rd". Consultant $3,741K Staff $150K ICAP $409K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. Change in Scope. | Item(s) Approved. Contingent upon approval by MAG Regional Council expected in February 2023. |
PRB Meeting Date: 10/18/2022 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
10/21/2022 8:09:52 AM | Carlos Lopez | (602) 712-4786 | 206 S 17th Ave, 300, 310B |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - Dirk Lay Rd | Widening | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601D | 6 | 010-C(227)T |
16. Original Program Budget: $5,170,000 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$5,170,000 | ($400,000) (0%) | $4,770,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5170 Item #:100965 ( ) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387 | $ -400 Item #:72323 (FY20 General Fund Appropriation ) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Decrease budget. |
26. JUSTIFICATION |
Funds are not needed to complete the design of this project. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 5/26/2020 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/3/2020 11:48:53 AM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295., 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
SR 587 - Dirk Lay Rd | Widening | LR1P | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pinal | 176 | F033601D | 6 |
16. Original Program Budget: $0 | 17. Original Program Item #: 101838 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $5,170,000 (0%) | $5,170,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 5170 Item #:100965 (Only need $5.37M) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387 |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish New Project |
26. JUSTIFICATION |
I-10 is planned to be widened by one lane in each direction throughout the project limits. Bridges at Dirk Lay and Gas Line Road will require replacement to accommodate the roadway widening. The scope of design work will include geotechnical investigation, roadway, structures, drainage, traffic control, signing, striping and erosion control at a minimum. The consultant will also prepare all information necessary to obtain environmental clearance, ROW clearance, and utility clearance. Consultant $4,354K Staff $350K ICAP $466K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |