PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 5/7/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/7/2024 9:57:25 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DIRK LAY RD - SOUTH OF SR 387 WIDEN ROADWAY LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701C 5.5 010-C(228)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $100,755,000 (0%) $100,755,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 58283 Item #:DT55900 (Laws 2022, Chapter 309 (HB 2858)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 2025  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
Construct roadway widening from Dirk Lay Rd to S. of SR 387 on I-10. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/19/2024 2:40:17 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DIRK LAY RD - SOUTH OF SR 387 WIDENING LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701U 6 010-C(228)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $1,000,000 (0%) $1,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1000 Item #:103007 (I-10 Riggs to SR 387 State 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Subphase
26. JUSTIFICATION
Work will include relocation of utilities at the State Route 387 intersection with I-10. ICAP is included in the request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/19/2024 2:39:57 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DIRK LAY RD - SOUTH OF SR 387 WIDENING LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701D 6 010-C(228)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,850,000 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,850,000 $700,000 (0%) $5,550,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #:DT55990 (.) FY:0 FundSRC: Desc: $ 700 Item #:103007 (I-10 Riggs Rd - SR387 State 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget, Update Scope
26. JUSTIFICATION
Additional scope items will include: Plant inventory, aesthetics, Geotech Enviro Clearance, Section 404 for F0336 and F0337, SR 387 TI scoping memo, Pipe lining/MOT exhibits, PS&E for culvert replacements, Resubmit Stage III (60pct) deliverables, and combine/Bid F0336 and F0337 as a single construction project. Staff: $50k Consultant: $582K ICAP $68K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 2/27/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/27/2024 10:24:48 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DIRK LAY RD - SOUTH OF SR 387 WIDENING LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701D 6 010-C(228)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,700,000 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,700,000 $150,000 (0%) $4,850,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 700 Item #:DT55990 (.) FY:0 FundSRC: Desc: $ 150 Item #:72324 (DT55900 I-10 Widening Legislative Appropriation FY 21 SB1820) FY:2024 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget, Update Scope
26. JUSTIFICATION
Additional scope item will include Freeway Management System Coordination and design. The design work will include plans, specs, and estimates supporting new FMS infrastructure. Consultant $135K ICAP $15K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 1/24/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/25/2023 12:02:27 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DIRK LAY RD - SOUTH OF SR 387 WIDENING LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701D 6 010-C(228)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $4,000,000 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$4,000,000 $700,000 (0%) $4,700,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4000 Item #:100965 (.) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387 $ 700 Item #:DT55900 (DT55900 I-10 Widening Legislative Appropriation FY 21) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget, Update Scope
26. JUSTIFICATION
Additional scope items will include video existing drainage culverts, re-evaluate alternative TI configurations at SR 387, and native plant inventory. The design work will include additional geotechnical investigation, roadway, structures, and drainage. Consultant $583K Staff $50K ICAP $67K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved. Contingent upon approval by MAG Regional Council expected in February 2023.


PRB Meeting Date: 5/26/2020
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/3/2020 11:50:09 AM Trent Kelso (602) 712-6685 205 S 17th Ave, 295., 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
Dirk Lay Rd - South of SR 387 Widening LQ1P
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 10 Pinal 181.5 F033701D 6  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 101837
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $4,000,000 (0%) $4,000,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4000 Item #:100965 (Only need 4M for design) FY:2020 FundSRC:. Desc:SR 202L (Santan) - SR 387  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
I-10 is planned to be widened by one lane in each direction throughout the project limits. Improvements will be needed at SR 387 interchange to accommodate the widening including ramp reconfiguration and structure widening. The scope of design work will include geotechnical investigation, roadway, structures, drainage, traffic control, signing, striping and erosion control at a minimum. The consultant will also prepare all information necessary to obtain environmental clearance, ROW clearance, and utility clearance. Consultant $3,340K Staff $300K ICAP $360K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation