PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 2/11/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/13/2025 8:57:24 AM | Arash Ghazanfari | (602) 712-8336 | 205 S 17TH AVE, 233, NONE |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
DAVIS RD; MP5 & MP13 | PAVEMENT & DRAINAGE REHABILITATION | LM1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 0000 | Cochise | CCH | T049701C | 1.61 | CCH-0(207)T |
16. Original Program Budget: $3,068,000 | 17. Original Program Item #: 103919 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$3,068,000 | $0 (0%) | $3,068,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | IGA 23-0009419-I |
$ 2893 Item #:103919 (Federal earmark (CDS23)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | 26 | |
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 4/30/2025 | 23a. Bid Adv Date: | 9/15/2025 |
25. DESCRIPTION OF REQUEST |
Defer project to FY26 |
26. JUSTIFICATION |
The project will be designed by Cochise county and the County is in the process of executing the design contract with the consultant firm. An advertisement date in FY25 is not feasible. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in FY. Change in Schedule. | Item(s) Approved. |
Arizona Department of Transportation |