PRB Meeting Date: 3/3/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2026 2:27:26 PM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DAVIS RD; MP5 & MP13 PAVEMENT & DRAINAGE REHABILITATION LM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Cochise CCH T049701C 0.61 CCH-0(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,068,000 17. Original Program Item #: 103919
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,068,000 $0 (0%) $3,068,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 23-0009419-
$ 2893 Item #:103919 (Federal earmark (CDS23)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 8/31/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change in Project Name. Change in Project Limit.
26. JUSTIFICATION
This request is to change project name and project limit to be only at MP5 and exclude MP13 from the project. During cultural survey, the environmental team sub-consultant found a large site at MP13 containing artifacts that were not found during a 2009 cultural survey for this same project. The CDS funding expires in September of 2026 and there is not enough time to issue environmental clearance if MP13 is included in the project. Change project name to: "DAVIS RD; MP5"
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Project Name/Location. Item(s) Approved.


PRB Meeting Date: 2/10/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2026 2:55:20 PM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DAVIS RD; MP5 & MP13 PAVEMENT & DRAINAGE REHABILITATION LM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Cochise CCH T049701C 1.61 CCH-0(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,068,000 17. Original Program Item #: 103919
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,068,000 $0 (0%) $3,068,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 23-0009419-I
$ 2893 Item #:103919 (Federal earmark (CDS23)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 9/15/2025 23a. Bid Adv Date: 8/31/2026

25. DESCRIPTION OF REQUEST
Change Schedule.
26. JUSTIFICATION
This request is to change construction of the project from FY26 to FY27. During cultural survey, the environmental team sub-consultant found a large site containing artifacts that were not found during a 2009 cultural survey for this same project. As a result, more investigation than was initially expected is required in order to complete the environmental clearance.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


PRB Meeting Date: 2/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
2/13/2025 8:57:24 AM Arash Ghazanfari (602) 712-8336 205 S 17TH AVE, 233, NONE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
DAVIS RD; MP5 & MP13 PAVEMENT & DRAINAGE REHABILITATION LM1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 0000 Cochise CCH T049701C 1.61 CCH-0(207)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,068,000 17. Original Program Item #: 103919
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,068,000 $0 (0%) $3,068,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: IGA 23-0009419-I
$ 2893 Item #:103919 (Federal earmark (CDS23)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 4/30/2025 23a. Bid Adv Date: 9/15/2025

25. DESCRIPTION OF REQUEST
Defer project to FY26
26. JUSTIFICATION
The project will be designed by Cochise county and the County is in the process of executing the design contract with the consultant firm. An advertisement date in FY25 is not feasible.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.