PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 7/28/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
8/4/2026 8:36:48 AM Myrna Bondoc (602) 712-7622 206 S 17TH AVE, , 304M
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-10 SPLIT TO MCDOWELL RD DCR LJ1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 194 F091401L 7 NA
PROJECT REQUEST SUMMARY
16. Original Program Budget: $31,003,000 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$31,003,000 $0 (0%) $31,003,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 18861 Item #:8890 ($18,860,679) FY:2020 FundSRC:. Desc:I-10 SPLIT - 19th AVE  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project.
26. JUSTIFICATION
This project will develop a Design Concept Report (DCR) for the ultimate build of I-17 from the I-I0 Split to McDowell Road.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation