PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/8/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/10/2025 10:34:59 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MEDICINE WAY - MP 275.7 CONSTRUCT PASSING LANE LG1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 70 Graham 274.5 F069801C 1.1 070-A(226)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104175
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $4,951,000 (0%) $4,951,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 4951 Item #:73325 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 5/9/2025 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 6/22/2025

25. DESCRIPTION OF REQUEST
Establish new Construction Project
26. JUSTIFICATION
This SE District project involves the construction of a passing lane on US 70, from milepost 274.55 to 275.6. The project will be delivered in the 4th quarter of FY 2025. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 9/17/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/18/2024 8:45:21 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MEDICINE WAY - MP 275.7 CONSTRUCT PASSING LANE LG1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 70 Graham 274.6 F069801C 1.1 070-A(226)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104175
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $0 (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
 

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 4/9/2025 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 5/9/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
FYI
26. JUSTIFICATION
The project involves the construction of a passing lane on US 70, from milepost 274.55 to 275.6, classified as a Minor Program Project. There is a potential need for an increase in construction funding due to higher-than-expected roadway excavation and the application of the TERO tax. The current Stage II construction estimate stands at $5,967,000. The project is anticipated to be delivered in the 4th quarter of FY 2025.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
FYI/Guidance. CONTINUE DESIGN WORK


PRB Meeting Date: 9/12/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/14/2023 8:34:39 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MEDICINE WAY - MP 275.7 CONSTRUCT PASSING LANE LG1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 70 Graham 274.6 F069801D 1.1 070-A(226)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 104175
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $529,000 (0%) $529,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 529 Item #:73324 ( ) FY:2024 FundSRC:. Desc:STATEWIDE MINOR PROJECTS  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project
26. JUSTIFICATION
This is a Minor Program Project for Construction of a Passing Lane on US 70 from MP 274.55 to MP 275.65. Staff - $363K consultant - $115K ICAP - $51K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation