PRB Meeting Date: 5/6/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/8/2025 10:48:29 AM Judah Cain , ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SKYLINE DR; SR90 - LANDFILL ENTRANCE ROADWAY RECONSTRUCTION LD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Cochise HCY T050301C 0.0 STBGHCY-0(200)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $2,095,000 17. Original Program Item #: 103379
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$2,095,000 $0 (0%) $2,095,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009397-I, 25-0011042-I
$ 500 Item #:103379 (STBGP Funding) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 11/5/2025

25. DESCRIPTION OF REQUEST
Defer project.
26. JUSTIFICATION
The need for right-of-way acquisitions has required changing the construction advertisement to the second quarter of fiscal year 26. The right-of-way clearance is scheduled for October 9, 2025.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox