| PRB Meeting Date: 1/14/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/16/2025 11:33:26 AM | Jane Gauger | (602) 712-4052 | 205 S 17th Ave, Rm 357, MD 618E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 75TH AVE. - 99TH AVE, US 60 | RAIL-HIGHWAY SAFETY UPGRADES | KV1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 148.0 | F032901X | 4.0 | 060-B(228)T |
| 16. Original Program Budget: $1,865,000 | 17. Original Program Item #: 101792 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $1,865,000 | $895,000 (0%) | $2,760,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 1379 Item #:72620 (90/10 match) FY:2020 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING | $ 415 Item #:72625 (90/10 match) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase budget. |
| 26. JUSTIFICATION |
| Costs for BNSF Railway to complete the Advanced Preemption construction work have increased due to price increases in the construction market. The original scope of work has not changed and this work is eligible for the Section 130 program. ICAP is included. Funding is the 90/10 cost split. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 5/16/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/18/2023 8:12:39 AM | Jane Gauger | (602) 712-4052 | 205 S 17th Ave, Rm 357 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 75TH AVE - 99TH AVE, US60 | RAIL-HIGHWAY SAFETY UPGRADES | KV1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 148.0 | F032901X | 0.1 | 060-B(228)T |
| 16. Original Program Budget: $1,705,000 | 17. Original Program Item #: 101792 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $1,705,000 | $160,000 (0%) | $1,865,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 1379 Item #:72620 (90/10 Match ) FY:2020 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING | $ 160 Item #:72323 (90/10 Match) FY:2023 FundSRC:. Desc:CONTINGENCY | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 23 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase budget |
| 26. JUSTIFICATION |
| Costs for the railroad to complete the advanced preemption work have increased due to price escalation in the construction market. The original scope of work has not changed and this work is eligible for the Section 130 program. Includes ICAP. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 5/16/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/18/2023 8:12:11 AM | Jane Gauger | (602) 712-4052 | 205 S 17th Ave, Rm 357 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 75TH AVE - 99TH AVE, US60 | RAIL-HIGHWAY SAFETY UPGRADES | KV1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 148.0 | F032901D | 0.1 | 060-B(228)T |
| 16. Original Program Budget: $121,000 | 17. Original Program Item #: 101792 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $121,000 | $119,000 (0%) | $240,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 121 Item #:72620 (90/10 Match ) FY:2020 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING | $ 119 Item #:72323 (90/10 Match) FY:2023 FundSRC:. Desc:CONTINGENCY | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Increase budget |
| 26. JUSTIFICATION |
| Costs to complete the advanced preemption upgrade work at 6 BNSF crossings along US60/Grand Avenue are higher than the amount FHWA authorized. Costs for the ADOT controllers and materials to communicate with the railroad signal are higher due to market price escalations. The original scope of work has not changed and this work is eligible for the Section 130 program. Includes ICAP. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 4/14/2020 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/24/2020 7:57:11 AM | Jane Gauger | 205 S 17th Ave, RM: 357, | (602) 712-4052 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 75th Ave - 99 Ave, Peoria | Install Advanced Preemption Systems | KV1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 148 | F032901D | 4.0 | 060-B(228)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 101792 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $121,000 (0%) | $121,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 121 Item #:72620 ( ) FY:2020 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish a new project. |
| 26. JUSTIFICATION |
| Project will install Advanced Preemption Systems at 6 BNSF crossings along US60 in Peoria. Staff- oversight, clearances = $60k Cost for controllers = $50k ICAP = $11k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 4/14/2020 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/24/2020 7:57:39 AM | Jane Gauger | 205 S 17th Ave, RM 357, | (602) 712-4052 |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| 75th Ave - 99th Ave, Peoria | Install Advanced Preemption Systems | KV1P | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Phoenix | 60 | Maricopa | 148 | F032901X | 4.0 | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 101792 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $1,379,000 (0%) | $1,379,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 1379 Item #:72620 ( ) FY:2020 FundSRC:. Desc:RAILWAY HIGHWAY CROSSING | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish a new project. |
| 26. JUSTIFICATION |
| Project will install Advanced Preemption Systems at 6 BNSF crossings along US60 in Peoria. BNSF - $1,254k ICAP - $125k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |