PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 12/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/10/2024 9:20:54 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
AJO WAY; BENSON HWY - I-10 STREET LIGHTING KI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima TUC T047901C 0.3 HSIPTUC-0(276)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $1,045,000 17. Original Program Item #: 103610
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$1,045,000 ($1,045,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 1045 Item #:103610 (100pct VRU funds) FY:0 FundSRC: Desc: $ -1045 Item #:70125 (100pct VRU funds) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 7/25/2024 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Delete project
26. JUSTIFICATION
The proposed work for T0479 is in conflict with a new major ADOT Traffic Interchange (TI) Design Build project scheduled to take place in the same area over the next several years. The City of Tucson requested to delete this project. The city will reassess what needs to be done, after the TI project is completed.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Delete Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 12/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/10/2024 9:18:39 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
AJO WAY; BENSON HWY - I-10 STREET LIGHTING KI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima TUC T047903D 0.3 HSIPTUC-0(276)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $252,000 17. Original Program Item #: 103610
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$252,000 ($252,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 252 Item #:103610 (100 percent VRU funding. $251,964) FY:0 FundSRC: Desc: $ -252 Item #:70125 (100pct VRU funds $251,964) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Delete project
26. JUSTIFICATION
The proposed work for T047903D is in conflict with a new major ADOT Traffic Interchange (TI) Design Build project scheduled to take place in the same area over the next several years. The City of Tucson requested to delete this project. The city will reassess what needs to be done, after the TI project is completed.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Delete Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 12/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/10/2024 9:19:56 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
AJO WAY; BENSON HWY - I-10 STREET LIGHTING KI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima TUC T047901D 0.3 HSIPTUC-0(276)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,000 17. Original Program Item #: 103610
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,000 ($10,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10 Item #:103610 (100 percent VRU funding. $9,880) FY:0 FundSRC: Desc: $ -10 Item #:70125 (100pct VRU funds $9,880) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Delete project
26. JUSTIFICATION
The proposed work for T047901D is in conflict with a new major ADOT Traffic Interchange (TI) Design Build project scheduled to take place in the same area over the next several years. The City of Tucson requested to delete this project. The city will reassess what needs to be done, after the TI project is completed.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Delete Project. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 8/22/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
8/25/2023 11:05:48 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
AJO WAY; BENSON HWY - I-10 STREET LIGHTING KI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima TUC T047901D 0.3 HSIPTUC-0(276)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $10,000 17. Original Program Item #: 103610
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$10,000 $0 (0%) $10,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 10 Item #:103610 (100 percent HSIP VRU funding.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
The purposed of this project is to improve safety for all roadway users. This project consists of new street lighting along the corridor of Ajo Way, from Benson Hwy to the I-10 ramp. Work includes street light foundation, conduit, wiring, electrical services. City of Tucson CA project. 100pct HSIP VRU funds. Staff Charges - $10K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 8/22/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
8/25/2023 11:06:08 AM Dana Cherry (602) 712-7030 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
AJO WAY; BENSON HWY - I-10 STREET LIGHTING KI1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Tucson 0000 Pima TUC T047903D 0.3 HSIPTUC-0(276)D
PROJECT REQUEST SUMMARY
16. Original Program Budget: $253,000 17. Original Program Item #: 103610
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$253,000 $0 (0%) $253,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 253 Item #:103610 (100 percent HSIP VRU funding.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
The purposed of this project is to improve safety for all roadway users. This project consists of new street lighting along the corridor of Ajo Way, from Benson Hwy to the I-10 ramp. Work includes street light foundation, conduit, wiring, electrical services. City of Tucson CA project. 100pct HSIP VRU funds. Design - $252,185.00
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox