PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 1/28/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 1/30/2025 8:55:51 AM | Jeffrey Davidson | (602) 712-8534 | 205 S 17th Ave, 295, 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CROSS CANYON - SUMMIT | PAVEMENT PRESERVATION | KA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 264 | Apache | 459 | F069301C | 6 | 264-A(224)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104076 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $4,200,000 (0%) | $4,200,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 4200 Item #:72325 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 25 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new construction project |
| 26. JUSTIFICATION |
| This project will improve the pavement surface conditions with a Mill and Replace with a Cape Seal & spot improvements. The type of bituminous material for the hot-applied chip seal coat will be PMAR (Polymer Modified Asphalt Rubber) Type 2 (PG 58-28) instead of PG 64-28 TR+. This Request includes ICAP |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 8/27/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 8/29/2024 8:39:39 AM | Jeffrey Davidson | (602) 712-8534 | 205 S 17th Ave, 295, 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CROSS CANYON - SUMMIT | PAVEMENT PRESERVATION | KA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 264 | Apache | 459 | F069301C | 6 | 264-A(224)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104076 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $3,600,000 (0%) | $3,600,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 3400 Item #:74825 (STBGP Flex ($3,394,800)) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 25 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new construction project |
| 26. JUSTIFICATION |
| This Project will improve the pavement surface conditions with a Mill and Replace, a Cape Seal & spot improvements. This Request includes ICAP |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |
| PRB Meeting Date: 4/16/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/16/2024 10:58:31 AM | Jeffrey Davidson | (602) 712-8534 | 205 S 17th Ave, 295, 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CROSS CANYON - SUMMIT | PAVEMENT PRESERVATION | KA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 264 | Apache | 459 | F069301C | 6 | 264-A(224)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104076 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $4,200,000 (0%) | $4,200,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 4200 Item #:74824 ( ) FY:2024 FundSRC:. Desc:MINOR & PREVENTATIVE PAVEMENT PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | 24 | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new construction project |
| 26. JUSTIFICATION |
| This Pavement Project will improve the pavement surface conditions with a Mill and Replace with a Cape Seal & spot improvements. This Request includes ICAP |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |
| PRB Meeting Date: 7/25/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 7/28/2023 2:11:05 PM | Jeffrey Davidson | (602) 712-8534 | 205 S 17th Ave, 295, 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| CROSS CANYON - SUMMIT | PAVEMENT LIFE EXTENSION | KA1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Flagstaff | 264 | Apache | 459 | F069301D | 6 | 264-A(224)T |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 104076 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $154,000 (0%) | $154,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 154 Item #:74824 ( ) FY:2024 FundSRC:. Desc:MINOR & PREVENTATIVE PAVEMENT PRESERVATION | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| This Pavement Project will improve the pavement surface conditions with a Mill and Replace Friction Course & spot improvements. Consultant: $75K Staff: $64K ICAP: $15K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
| Arizona Department of Transportation |