| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/23/2025 9:14:51 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| NORTH OF FLORENCE - QUEEN VALLEY | PASSING LANES | JE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 79 | Pinal | 140.0 | F070701D | 8.0 | 079-A(214)T |
| 16. Original Program Budget: $504,000 | 17. Original Program Item #: 103644 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $504,000 | $0 (0%) | $504,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 475 Item #:103644 (94.3pct HSIP) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Add Minor Scope. |
| 26. JUSTIFICATION |
| The Design Team and District recommend applying a full-width microseal to the existing roadway rather than a 2-foot patch over the pavement markings area followed by a slurry seal. A narrow patch would create a new joint directly in the wheel path, which is likely to deteriorate rapidly under traffic loads. The proposed minor scope change is a good pavement life extension investment. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 10/21/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 10/23/2025 9:26:04 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| NORTH OF FLORENCE - QUEEN VALLEY | PASSING LANES | JE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 79 | Pinal | 140.0 | F070701C | 8.0 | HSIP079-A(214)T |
| 16. Original Program Budget: $7,873,000 | 17. Original Program Item #: 103644 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $7,873,000 | $200,000 (0%) | $8,073,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 7424 Item #:103644 (HSIP 94.3) FY:0 FundSRC: Desc: | $ 200 Item #:74826 ( ) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 26 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 3/20/2026 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Add Minor Scope. Increase Budget. |
| 26. JUSTIFICATION |
| The Design Team and District recommend applying a full-width microseal to the existing roadway rather than a 2-foot patch over the pavement markings area followed by a slurry seal. A narrow patch would create a new joint directly in the wheel path, which is likely to deteriorate rapidly under traffic loads. The proposed minor scope change is a good pavement life extension investment. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. Subject to PPAC Approval. |
| PRB Meeting Date: 2/27/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/1/2024 10:19:30 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| NORTH OF FLORENCE - QUEEN VALLEY | PASSING LANES | JE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 79 | Pinal | 140.0 | F070701D | 8.0 | 079-A(214)T |
| 16. Original Program Budget: $577,000 | 17. Original Program Item #: 103644 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $577,000 | ($73,000) (0%) | $504,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 544 Item #:103644 (94.3pct HSIP) FY:0 FundSRC: Desc: | $ -73 Item #:70124 ( ) FY:2024 FundSRC:. Desc:MODERNIZATION | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new design project |
| 26. JUSTIFICATION |
| This is an HSIP Program Project for Construction of a Passing Lane on SR 79 from NB MP 140.45 to 140.95, SB MP 143.65 - 144.00, NB 145.81 - 146.20, SB MP 147.38 - 147.75 Staff - $364K Consultant - $91K ICAP - $49K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 12/19/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 12/22/2023 10:23:47 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| NORTH OF FLORENCE - QUEEN VALLEY | PASSING LANES | JE1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Globe | 79 | Pinal | 140.0 | F070701D | 8.0 | 079-A(214)T |
| 16. Original Program Budget: $577,000 | 17. Original Program Item #: 103644 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $577,000 | ($35,000) (0%) | $542,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 544 Item #:103644 (94.3pct HSIP) FY:0 FundSRC: Desc: | $ -35 Item #:70124 ( ) FY:2024 FundSRC:. Desc:MODERNIZATION | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new design project |
| 26. JUSTIFICATION |
| This is an HSIP Program Project for Construction of a Passing Lane on SR 79 from NB MP 140.45 to 140.95, SB MP 143.65 - 144.00, NB 145.80 - 146.20, SB MP 147.38 - 147.75 Staff - $350K Consultant - $126K ICAP - $51K |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Request Withdrawn. |