PRB Meeting Date: 2/27/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/1/2024 10:19:30 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
NORTH OF FLORENCE - QUEEN VALLEY PASSING LANES JE1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 79 Pinal 140.0 F070701D 8.0 079-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $577,000 17. Original Program Item #: 103644
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$577,000 ($73,000) (0%) $504,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 544 Item #:103644 (94.3pct HSIP) FY:0 FundSRC: Desc: $ -73 Item #:70124 ( ) FY:2024 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project
26. JUSTIFICATION
This is an HSIP Program Project for Construction of a Passing Lane on SR 79 from NB MP 140.45 to 140.95, SB MP 143.65 - 144.00, NB 145.81 - 146.20, SB MP 147.38 - 147.75 Staff - $364K Consultant - $91K ICAP - $49K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 12/19/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/22/2023 10:23:47 AM Pei-jung Li (602) 712-8708 205 S 17th Ave, , 605E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
NORTH OF FLORENCE - QUEEN VALLEY PASSING LANES JE1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 79 Pinal 140.0 F070701D 8.0 079-A(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $577,000 17. Original Program Item #: 103644
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$577,000 ($35,000) (0%) $542,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 544 Item #:103644 (94.3pct HSIP) FY:0 FundSRC: Desc: $ -35 Item #:70124 ( ) FY:2024 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new design project
26. JUSTIFICATION
This is an HSIP Program Project for Construction of a Passing Lane on SR 79 from NB MP 140.45 to 140.95, SB MP 143.65 - 144.00, NB 145.80 - 146.20, SB MP 147.38 - 147.75 Staff - $350K Consultant - $126K ICAP - $51K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.