PRB Meeting Date: 3/10/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2026 11:52:50 AM Patrick O`leske (602) 568-3357 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
KINISHIBA RD - S. MIDDLE ST, CANYON DAY INSTALL STREET LIGHTING JD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 73 Gila 333.2 F069101C 0.8 HSIP073-A(210)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $515,000 17. Original Program Item #: 103655
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$515,000 $0 (0%) $515,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 515 Item #:103655 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 2/13/2026 23a. Bid Adv Date: 5/15/2026

25. DESCRIPTION OF REQUEST
Change Schedule to Q4.
26. JUSTIFICATION
Project was originally scheduled to deliver in FY 26 Q3, but due to delays in receiving SUE files from the on-call consultant, and additional time required to draft the utility service agreement with NEC, the project will not be ready until mid FY 26 Q4.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved.


PRB Meeting Date: 3/18/2025
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/20/2025 11:08:55 AM Patrick O`leske (480) 416-8367 205 S 17TH AVE
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
KINISHIBA RD - S. MIDDLE ST, CANYON DAY INSTALL STREET LIGHTING JD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 73 Navajo 333.2 F069101C 0.8  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $515,000 17. Original Program Item #: 103655
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$515,000 $0 (0%) $515,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 515 Item #:103655 (100pct VRU) FY:0 FundSRC: Desc: $ -515 Item #:70125 (100pct VRU) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 6/13/2025 23a. Bid Adv Date: 12/2/2025

25. DESCRIPTION OF REQUEST
Defer to FY26.
26. JUSTIFICATION
Project will not be ready to advertise in FY25. Design team experienced several-month delay in obtaining needed survey deliverables due to limited resources, and additional delays in the design process due to having to convert from solar-powered lighting to electricity-powered.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 3/12/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/14/2024 2:09:06 PM Patrick O`Leske (602) 568-3357 205 S 17th Ave
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
KINISHIBA RD - S. MIDDLE ST, CANYON DAY INSTALL STREET LIGHTING JD1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Globe 73 Gila 333.2 F069101D 0.8  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $351,000 17. Original Program Item #: 103655
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$351,000 ($113,000) (0%) $238,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 351 Item #:103655 (100pct VRU) FY:0 FundSRC: Desc: $ -113 Item #:70124 (100pct VRU) FY:2024 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
HSIP project to install 0.8 miles of new lighting along SR-73, between MP 333.2 to MP334. Staff - $155k Env. Consultant - $60k ICAP - $23k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox