1/29/2024 7:25:56 AM Heidi Yaqub (602) 712-7644 206 S 17th Ave, , 310B
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
TRUWOOD DR - SUNDOG RANCH RD ITS IMPROVEMENTS JA1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Prescott 69 Yavapai 287 F072601L 3  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103704
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $250,000 (0%) $250,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 250 Item #:77824 (Statewide Freight Program) FY:2024 FundSRC:. Desc:STATE PLANNING & RESEARCH  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Scoping Subphase.
26. JUSTIFICATION
The scoping study will assess potential ITS Improvements within the defined SR 69 corridor. It will also consider a synchronized network to ensure signal progression with the adaptive signal system and the CYMPO completed study to implement adaptive signal control along this corridor mesh and are maximized. Part of the study would also look at existing fiber along corridor and the feasibility of fiber expansion to facilitate tying corridor signals into ADOT�s existing signal network. The scoping study should also include reviewing whether to add a smaller blank-out-sign type DMS closer to Fain Road or review the feasibility of moving the existing DMS on SR69 closer to Fain Road in order to better divert unneeded traffic or freight movements that have destinations to the Chino Valley area.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox