PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 11/19/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/6/2024 2:24:30 PM CARMELO ACEVEDO / MYRNA BONDOC (480) 932-7319 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; VARIOUS LOCATIONS CONSTRUCT TRUCK PARKING IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069602C 999-A(571)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $14,000,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$14,000,000 $8,500,000 (0%) $22,500,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 14000 Item #:103701 ( ) FY:0 FundSRC: Desc: $ 550 Item #:79625 ( Subprogram 796 (Truck Parking)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
The project was under estimated. There are a total of four rest areas. Three rest areas have two sites and one has one site, for a total of seven sites. Reason for Increase: 1. Parks and Christensen Rest Areas, have been closed for 20 years and need extensive rehab to be repurposed for for safe truck parking with minimum amenities. 2. The recently completed Statewide Truck Parking Plan identified Parks Rest Area as a hot-spot for undesignated truck parking and needs to be expanded. 3. The original estimate is based on gravel lots. Multiple washes run through and near the Haviland RA making the site susceptible to erosion. Gravel lots are prone to erosion and rutting, which can lead to more frequent maintenance. A more resilient surface material is required. 4. Parks and Christensen are located near Flagstaff. Weather conditions require a surface material that can withstand freeze thaw cycles without annual maintenance and can be snow plowed. 3. Mobilization and traffic control was calculated per rest area than per site. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 6/11/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/11/2024 10:33:28 AM CARMELO ACEVEDO / MYRNA BONDOC (480) 932-7319 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; VARIOUS LOCATIONS CONSTRUCT TRUCK PARKING IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C 999-A(571)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $6,000,000 (0%) $22,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc: $ 3000 Item #:77824 (Freight Subprogram) FY:2024 FundSRC:. Desc:STATE PLANNING & RESEARCH  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
The project was under estimated. There are a total of four rest areas. Three of the four rest areas have two sites and one rest area has one site, at a total of seven sites. Reason for Increase: 1. EB & WB Parks and NB & SB Christensen, were originally planned to be repurposed without expansion. After the conclusion of the Statewide Truck Parking Plan the four sites were identified to be repurposed and expanded. 2. The estimates were based on gravel parking lots. Multiple washes run through and near the Haviland RA making the site susceptible to erosion. Gravel lots can be prone to erosion and rutting, which can lead to more frequent maintenance. A more resilient surface material is required to prevent erosion. 3. Mobilization and traffic control were calculated per rest area than per site. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 5/14/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/16/2024 10:25:07 AM CARMELO ACEVEDO / MYRNA BONDOC (480) 932-7319 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; VARIOUS LOCATIONS CONSTRUCT TRUCK PARKING IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C 999-A(571)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $8,000,000 (0%) $24,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc: $ 2500 Item #:70924 (CRP Subprogram) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
The project was under estimated. There are a total of four rest areas. Three of the four rest areas have two sites and one rest area has one site, at a total of seven sites. Reason for Increase: 1. EB&WB Parks and NB&SB Christensen, were originally planned to be repurposed without expansion. After the conclusion of the Statewide Truck Parking Plan the four sites were identified to be repurposed and expanded. 2. Some items, such as mobilization and traffic control, were estimated for each rest area, not for each site. 3. Locations are far apart and remote, driving up the cost to construct. 4. Surface material options estimated are not suited for certain conditions. For instance, gravel is not suited for snow because it cannot be snow plowed. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 4/23/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/23/2024 2:34:34 PM CARMELO ACEVEDO / MYRNA BONDOC (480) 932-7319 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; VARIOUS LOCATIONS CONSTRUCT TRUCK PARKING IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C 999-A(571)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $8,000,000 (0%) $24,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc: $ 2500 Item #:70924 (CRP Subprogram) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
The project was under estimated. There are a total of four rest areas. Three of the four rest areas have two sites and one rest area has one site, at a total of seven sites. Reason for Increase: 1. EB&WB Parks and NB&SB Christensen, were originaly planned to be repurposed without expansion. After the conclusion of the Statewide Truck Parking Plan the four sites were identified to be repurposed and expanded. 2. Some below the line items, such as, mobilization and traffic control, was estimated for each rest area not for each site. 3. Locations are far apart and remote, driving up the cost to construct. 4. Surface material options estimated are not suited for certain conditions. For instance, gravel is not suited for snow because it cannot be snow plowed. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 4/16/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/16/2024 11:32:40 AM CARMELO ACEVEDO / MYRNA BONDOC (480) 932-7319 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; VARIOUS LOCATIONS CONSTRUCT TRUCK PARKING IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C 999-A(571)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $8,000,000 (0%) $24,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc: $ 2500 Item #:70924 (CRP Subprogram) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget
26. JUSTIFICATION
The project was under estimated. There are a total of four rest areas. Three of the four rest areas have two sites and one rest area has one site, at a total of seven sites. Reason for Increase: 1. EB&WB Parks and NB&SB Christensen, were originaly planned to be repurposed without expansion. After the conclusion of the Statewide Truck Parking Plan the four sites were identified to be repurposed and expanded. 2. Some below the line items, such as, mobilization and traffic control, was estimated for each rest area not for each site. 3. Locations are far apart and remote, driving up the cost to construct. 4. Surface material options estimated are not suited for certain conditions. For instance, gravel is not suited for snow because it cannot be snow plowed. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Request Withdrawn.


PRB Meeting Date: 10/31/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/31/2023 9:52:32 AM Carmelo Acevedo (602) 712-4258 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; FIVE REST AREAS Construct Truck Parking IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $0 (0%) $16,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 24  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Construction Phase.
26. JUSTIFICATION
This is an Alternative Delivery Project to construct additional truck parking at five rest areas along I-40 and I-17. We are requesting to establish the construction phase. Federal approval has been granted for PE. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 10/17/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/18/2023 3:39:51 PM Carmelo Acevedo (602) 712-7622 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; FIVE REST AREAS Construct Truck Parking IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601D  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $333,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$333,000 $1,467,000 (0%) $1,800,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 333 Item #:103701 (.) FY:0 FundSRC: Desc: $ 1467 Item #:103701 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Budget
26. JUSTIFICATION
This is an Alternative Delivery Project to construct additional truck parking at five rest areas along I-40 and I-17. Funding is for the design of the subject project, including the consultant, to develop the construction agreements and pre-construction documents. Consultant: $1,210K Staff: $100K ICAP: $157K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 10/17/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
10/27/2023 8:31:20 AM Carmelo Acevedo (602) 712-4258 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; FIVE REST AREAS Construct Truck Parking IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601C  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $16,200,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$16,200,000 $0 (0%) $16,200,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 16200 Item #:103701 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year: 24  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Construction Phase.
26. JUSTIFICATION
This is an Alternative Delivery Project to construct additional truck parking at five rest areas along I-40 and I-17. We are requesting to establish the construction phase. Federal approval has been granted for PE. Design-builder: $14,267 Staff: $200 ICAP: $1,733
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Request Withdrawn.


PRB Meeting Date: 7/18/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/28/2023 7:13:33 AM Carmelo Acevedo (602) 712-7622 206 S 17th Ave,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
I-40 AND I-17; FIVE REST AREAS Construct Truck Parking IT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Flagstaff I-40, I-17 Coconino F069601D  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $333,000 17. Original Program Item #: 103701
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$333,000 $0 (0%) $333,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 333 Item #:103701 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Project
26. JUSTIFICATION
This is an Alternative Delivery Project to construct additional truck parking at five rest areas along I-40 and I-17. I-40: Parks NB & SB Rest Areas, Haviland EB & WB Rest Areas I-17: Christensen NB & SB Rest Areas, McGuireville NB & SB Rest Areas, Sunset Point Rest Area Consultant: $200K Staff: $100K ICAP: $33K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation