PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 4/15/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
4/18/2025 10:12:14 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CITY OF CASA GRANDE; FLORENCE BLVD AND COLORADO ST | INSTALL RAISED MEDIAN | II1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pinal | CSG | T047001C | 0.0 | CSG-0(213)T |
16. Original Program Budget: $412,000 | 17. Original Program Item #: 103883 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$412,000 | $102,000 (0%) | $514,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009427-I |
$ 389 Item #:103883 (HSIP ($388,624 94.3 pct)) FY:0 FundSRC: Desc: | $ -389 Item #:70125 (HSIP ($388,624 94.3 pct)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 6/26/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer Project to future FY Increase budget |
26. JUSTIFICATION |
This is a local HSIP project to install 300 ft. of raised median on Florence Blvd starting approximately 200 ft. west of Colorado St in the City of Casa Grande. The city requests to defer this project from FY25 to a future FY, due to financial constraints. The SCMPO Board approved adding some of their Federal funds to this project on March 11. The city has secured local matching funds for this project and the IGA is scheduled to go to the May 19 City Council Meeting. The city will provide the local funds to the Department on June 19. TIP ID CSG-23-01 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Schedule. DEFER TO FUTURE FY | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 3/11/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
3/11/2025 10:12:20 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CITY OF CASA GRANDE; FLORENCE BLVD AND COLORADO ST | INSTALL RAISED MEDIAN | II1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pinal | CSG | T047001C | 0.0 | CSG-0(213)T |
16. Original Program Budget: $413,000 | 17. Original Program Item #: 103883 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$413,000 | $107,000 (0%) | $520,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009427-I |
$ 389 Item #:103883 (HSIP ($ 388,624 94.3pct)) FY:0 FundSRC: Desc: | $ 5 Item #:OTHR25 ($5,077.23 1 (5.7pct local match for STBG from SCMPO)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 6/25/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new construction Project Increase Budget |
26. JUSTIFICATION |
This is local HSIP project for the installation 300� of raised median on Florence Blvd starting approximately 200� west of Colorado St in City of Casa Grande. Environmental clearance have been issued on Feb 28. The JPA amendment is currently in progress. The SCMPO TIP Amendment board is planning on March 11th and city council agenda for April 21st, 2025 TIP ID CSG-23-01 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Request Withdrawn. |
PRB Meeting Date: 2/25/2025 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/25/2025 3:23:32 PM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CITY OF CASA GRANDE; FLORENCE BLVD AND COLORADO ST | INSTALL RAISED MEDIAN | II1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pinal | CSG | T047001C | 0.0 | CSG-0(213)T |
16. Original Program Budget: $413,000 | 17. Original Program Item #: 103883 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$413,000 | $0 (0%) | $413,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009427-I |
$ 389 Item #:103883 (HSIP ($ 388,624 94.3pct)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 6/26/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new construction project |
26. JUSTIFICATION |
This is local HSIP project for the installation 300� of raised median on Florence Blvd starting approximately 200� west of Colorado St in City of Casa Grande. Environmental clearance is scheduled for issuance on Feb 28. The JPA amendment is currently in progress. TIP ID CSG-23-01 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Request Withdrawn. |
PRB Meeting Date: 2/6/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/8/2024 9:25:47 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CITY OF CASA GRANDE; FLORENCE BLVD AND COLORADO ST | INSTALL RAISED MEDIAN | II1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pinal | T047003D | 0.0 | CSG-0(213)T |
16. Original Program Budget: $146,000 | 17. Original Program Item #: 103883 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$146,000 | $0 (0%) | $146,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009486 |
$ 138 Item #:103883 (HSIP ($ 137,607 94.3pct)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new design project |
26. JUSTIFICATION |
This is local HSIP project for the installation 300� of raised median on Florence Blvd starting approximately 200� west of Colorado St in City of Casa Grande. The Joint Project Agreements (JPAs) were approved and signed during the Council meeting on January 24, 2024. TIP ID CSG-23-01 Consultant- $146K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 2/6/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
2/8/2024 9:25:19 AM | Pei-jung Li | (602) 712-8708 | 205 S 17th Ave, , 605E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CITY OF CASA GRANDE; FLORENCE BLVD AND COLORADO ST | INSTALL RAISED MEDIAN | II1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 0000 | Pinal | T047001D | 0.0 | CSG-0(213)T |
16. Original Program Budget: $30,000 | 17. Original Program Item #: 103883 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$30,000 | $0 (0%) | $30,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | 23-0009427-I |
$ 28 Item #:103883 (HSIP ($ 28,290.00 94.3pct)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a new design project |
26. JUSTIFICATION |
This is local HSIP project for the installation 300� of raised median on Florence Blvd starting approximately 200� west of Colorado St in City of Casa Grande. The Joint Project Agreements (JPA) was approved and signed during the Council meeting on January 24, 2024. TIP ID CSG-23-01 Staff- $30K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |