PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/3/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/5/2026 10:58:16 AM Lina Bearat (602) 538-5124 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 264 / IR 4, PHASE II CONSTRUCT PEDESTRIAN PATH ID1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 264 Navajo 380.0 F067801D 1.2 264-A(223)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $301,000 17. Original Program Item #: 103654
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$301,000 $60,000 (0%) $361,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 301 Item #:103654 (VRU 100pct) FY:0 FundSRC: Desc: $ 60 Item #:70126 (VRU 100pct) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 4/28/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase Design Budget.
26. JUSTIFICATION
This project is to build a path on SR 264. Based on consultation with the Hopi Tribe, the project team has recommended to add lighting along the entire path for safety enhancement for vulnerable users. The scope change and additional coordination with Hopi Tribe for environmental consultation requires additional design funds. Staff: $56k ICAP: $4k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in Scope. Item(s) Approved.


PRB Meeting Date: 3/3/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2026 2:29:28 PM Lina Bearat (602) 538-5124 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 264 / IR 4, PHASE II CONSTRUCT PEDESTRIAN PATH ID1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 264 Navajo 380.0 F067801C 1.2 264-A(223)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $755,000 17. Original Program Item #: 103654
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$755,000 $250,000 (0%) $1,005,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 755 Item #:103654 (VRU 100pct - Current FY26 funding) FY:0 FundSRC: Desc: $ 1005 Item #:70127 (VRU 100 - Add funds to FY 27) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 27  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 4/28/2026 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Change in Scope. Increase Budget. Change Fiscal Year.
26. JUSTIFICATION
This project is to build a path on SR 264. Based on consultation with the Hopi Tribe, the project team has recommended to add lighting along the entire path for safety enhancement for vulnerable users. This change in scope needs additional funding to construct. The request is also to move the project from FY 26 to FY 27.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Scope. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 11/7/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/9/2023 8:40:30 AM Thomas Oreilly (602) 712-2587 205 S 17th Ave, 293, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 264 AT IR 4 CONSTRUCT PEDESTRIAN PATH ID1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 264 Navajo 380.0 F067801D 1.2 264-A(223)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $301,000 17. Original Program Item #: 103654
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$301,000 $0 (0%) $301,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 301 Item #:103654 (VRU ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish project
26. JUSTIFICATION
This project will extend a pedestrian path being constructed near the Hopi Cultural Center. Request to establish the project Name/Location as "SR 264 / IR 4, Phase II". Staff = $94K Consultant = $177K ICAP = $29K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox