PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 4/21/2026
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/12/2026 4:12:10 PM Ted Smithwick (602) 228-5378 205 S 17TH AVE, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
SR 95 - NW OF BOUSE PAVEMENT REHABILITATION HW1R
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 72 La Paz 13.1 F093401D 7.1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $13,158,000 17. Original Program Item #: 106164
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$13,158,000 $530,000 (0%) $13,688,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 530 Item #:72726 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 30 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Design Project.
26. JUSTIFICATION
This is design for a pavement rehabilitation project on SR 72 from SR 95 to Northwest of Bouse. Consultant - $100k Staff - $400k ICAP - $30k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation