PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 6/6/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/8/2023 3:11:08 PM Chris Rodriguez (602) 712-4642 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
VARIOUS LOCATIONS - STATEWIDE RWIS UPGRADE RWIS HU1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
999 Statewide 0.0 F067901D 0.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #:
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $350,000 (0%) $350,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 350 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish New Project
26. JUSTIFICATION
This project will upgrade Road Weather Information Systems (RWIS) at various locations. Consultant $267K Staff $50K ICAP $33K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation