PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 12/10/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/12/2024 10:07:24 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
S PALO VERDE BLVD - PRICE RD | CONSTRUCT RAISED MEDIANS | HS1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 95 | Mohave | 183.0 | F064801C | 3.4 | 095-C(228)T |
16. Original Program Budget: $4,050,000 | 17. Original Program Item #: 103636 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$4,050,000 | $866,000 (0%) | $4,916,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3819 Item #:103636 (94.3pct FEDERAL AID) FY:0 FundSRC: Desc: | $ 817 Item #:70125 (94.3pct HSIP ($816,638)) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 25 | 21a. Fiscal Year: | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 2/7/2025 | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
This HSIP project will construct raised medians on SR 95 in two segments from S. Palo Verde Boulevard to Industrial Boulevard (MP 183 to 184) and N. Palo Verde Boulevard to Chenowith Road (MP 186 to 188). Request increase in budget to cover additional reinforcing in the pinned concrete median curb. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 8/13/2024 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
8/15/2024 11:16:20 AM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
S PALO VERDE - INDUSTRIAL, N PALO VERDE - PRICE | CONSTRUCT RAISED MEDIANS | HS1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 95 | Mohave | 183.0 | F064801C | 3.4 | 095-C(228)T |
16. Original Program Budget: $4,050,000 | 17. Original Program Item #: 103636 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$4,050,000 | $0 (0%) | $4,050,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 3819 Item #:103636 (94.3pct FEDERAL AID) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Change project name |
26. JUSTIFICATION |
This HSIP project will construct raised medians on SR 95 in two segments from S. Palo Verde Boulevard to Industrial Boulevard (MP 183 to 184) and N. Palo Verde Boulevard to Chenowith Road (MP 186 to 188). Change project name to "S. PALO VERDE BLVD - PRICE RD" |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Change in Project Name/Location. | Item(s) Approved. |
PRB Meeting Date: 7/18/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
7/21/2023 1:10:11 PM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
S PALO VERDE - INDUSTRIAL, N PALO VERDE - PRICE | CONSTRUCT RAISED MEDIANS | HS1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Kingman | 95 | Mohave | 183.0 | F064801D | 3.4 | 095-C(228)T |
16. Original Program Budget: $439,000 | 17. Original Program Item #: 103636 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$439,000 | $20,000 (0%) | $459,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 414 Item #:103636 (94.3pct FEDERAL AID) FY:0 FundSRC: Desc: | $ 19 Item #:70124 (94.3pct FEDERAL AID) FY:2024 FundSRC:. Desc:MODERNIZATION |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This HSIP project will construct raised medians on SR 95 in two segments from MP 183 to 184 and MP 186 to 188. Staff $44k Consultant $370 ICAP $45 |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
Arizona Department of Transportation |