PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 12/9/2025 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 12/11/2025 1:23:37 PM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US95; COUNTY 20 1/2 ST - COUNTY 22ND ST | RAISED MEDIANS | HQ1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Yuma | 0000 | Yuma | SLS | T046501C | 1.0 | HSIPSLS-0(206)T |
| 16. Original Program Budget: $1,785,000 | 17. Original Program Item #: 103641 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $1,785,000 | $0 (0%) | $1,785,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009364 |
| $ 1785 Item #:103641 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | FY26 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 12/21/2025 | 23a. Bid Adv Date: | 1/30/2026 | |
| 25. DESCRIPTION OF REQUEST |
| Change Project Limits. Change Schedule. |
| 26. JUSTIFICATION |
| This project will construct raised medians on SR95 in the City of San Luis. The City has requested the scope be reduced to stay within the budget. Change Project Limits to: County 21st St - County 22nd St Request to move advertisement to FY26 Q3. |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Change in Project Name/Location. Change in Schedule. | Item(s) Approved. |
| PRB Meeting Date: 4/9/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/11/2024 2:01:06 PM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US95; COUNTY 20 1/2 ST - COUNTY 22ND ST | RAISED MEDIANS | HQ1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Yuma | 0000 | Yuma | SLS | T046503D | 0.0 | HSIPSLS-0(206)T |
| 16. Original Program Budget: $447,000 | 17. Original Program Item #: 103641 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $447,000 | $0 (0%) | $447,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009364 |
| $ 421 Item #:103641 (94.3pct HSIP) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish project. |
| 26. JUSTIFICATION |
| This project will construct raised medians on SR95 from MP 1.66 to 3.17 in the City of San Luis Consultant $446k ($421,238) Local match ($25,462) |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| PRB Meeting Date: 4/9/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | |||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 4/11/2024 2:00:42 PM | Chris Moore | (757) 469-6679 | 205 S 17th Ave, , |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US95; COUNTY 20 1/2 ST - COUNTY 22ND ST | RAISED MEDIANS | HQ1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Yuma | 0000 | Yuma | SLS | T046501D | 0.0 | HSIPSLS-0(206)T |
| 16. Original Program Budget: $30,000 | 17. Original Program Item #: 103641 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $30,000 | $0 (0%) | $30,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | 23-0009364 |
| $ 2 Item #:OTHR24 (5.7pct Local match) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish project. |
| 26. JUSTIFICATION |
| This project will construct raised medians on SR95 from MP 1.66 to 3.17 in the City of San Luis Staff $30k ($28,290) Local match ($1,710) |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |