PRB Meeting Date: 12/10/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/16/2024 2:14:09 PM Rashidul Haque (602) 712-7352 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MP8 - MP13, S OF DRY LAKE CONSTRUCT SHOULDERS & RUMBLE STRIPS HG1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 377 Navajo 8.0 F066101C 5.0 HSIP377-A(203)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $5,150,000 17. Original Program Item #: 103630
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$5,150,000 $8,851,000 (0%) $14,001,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 293 Item #:103630 (5.7 pct State match ($293,550)) FY:0 FundSRC: Desc: $ -4856 Item #:70126 (94.3 pct HSIP ($4,856,450)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 2026 21a. Fiscal Year: 2025  
22. Bid Pkg Rdy Date: 8/22/2025 22a. Bid Pkg Rdy Date: 4/30/2025 24. Verified all of the new funding sources
23. Bid Adv Date: 9/22/2025 23a. Bid Adv Date: 5/30/2025

25. DESCRIPTION OF REQUEST
Advance project to FY25 and Increase Budget, Change project name.
26. JUSTIFICATION
This request is to advance construction from FY26 to FY25 to advertise this project in FY25, and Increase Budget. Capacity exists to deliver this project in FY25. The project will be ready to deliver in FY25. The request to increase the budget is due to large quantity changes and unit price increases. The HSIP application estimate significantly underestimated items including roadway and drainage excavations, pipe work and pavement items. Change project name to "MP 8 - Phoenix Park Wash, S of Dry Lake".
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Project Name/Location. Change in Schedule. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 7/25/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/28/2023 1:54:11 PM Rashidul Haque (602) 712-7352 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
MP8 - MP13, S OF DRY LAKE CONSTRUCT SHOULDERS & RUMBLE STRIPS HG1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Holbrook 377 Navajo 8.0 F066101D 5.0 HSIP377-A(203)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $873,000 17. Original Program Item #: 103630
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$873,000 ($223,000) (0%) $650,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 823 Item #:103630 ( 94.3 pct HSIP) FY:0 FundSRC: Desc: $ -223 Item #:70124 ( ) FY:2024 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish Project
26. JUSTIFICATION
This is an in-house design Highway Safety Improvement project to widen shoulders and install rumble strips for the undivided two lane highway located south of Dry Lake. Construction in FY26. Staff :$487K Consultant: $100K ICAP: $63K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox