PRB Meeting Date: 8/15/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
8/17/2023 10:58:57 AM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
US 191 TI (ER) | PERMANENT BRIDGE REPAIR | HE1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 10 | Cochise | 331.0 | F067001C | 1.0 | 010-F(236)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 103996 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $10,000,000 (0%) | $10,000,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 10000 Item #:72324 (Emergency Relief Funds) FY:2024 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | 24 | ||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: | 8/31/2023 |
25. DESCRIPTION OF REQUEST |
Establish new project and change project name. |
26. JUSTIFICATION |
This project will construct the permanent repair at the westbound I-10 bridge with US 191. On May 3, 2023, the westbound I-10 bridge was damaged when a semi-tractor trailer hit the support structure. The ER declaration was signed on 05/24/2023. Emergency relief funds are requested for the reconstruction of the north pier and for the removal and replacement of the steel superstructure and bridge deck. For consistency with the federal authorization, the project name will be changed to `US 191 TI SW of Willcox`. ICAP is included in the request. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |
PRB Meeting Date: 6/6/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | (602) 712-7046 | ||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/12/2023 7:10:05 AM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
US 191 TI (ER) | PERMANENT BRIDGE REPAIR | HE1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 10 | Cochise | 331.0 | F067001D | 1.0 | 010-F(236)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 103996 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $829,000 (0%) | $829,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 829 Item #:72323 (Emergency Relief Funds) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
This project will construct the permanent repair at the westbound I-10 bridge with US 191. On May 3, 2023, the westbound I-10 bridge was damaged when a semi-tractor trailer hit the support structure. The ER declaration was signed on 5/24/2023. Staff: $650k Consultant: $100k ICAP: $79k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. |