PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/13/2025 8:48:38 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046001R 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $75,000 (0%) $75,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226-I
$ 71 Item #:103594 (HRRR 94.3 PCT ($70,725)) FY:0 FundSRC: Desc: $ 71 Item #:103594 (HRRR 94.3 pct ($70,725)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Fund 01R Subphase
26. JUSTIFICATION
Yavapai County is acquiring right of way from the Arizona State Land Department. The ROW funding is shown in the FY25 - FY29 Program per the previous PRB approval on 06/11/2024.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 3/11/2025
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/11/2025 10:50:00 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046001C 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,775,000 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,775,000 $0 (0%) $3,775,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226-I
$ 14 Item #:103594 (100 pct HRRR) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year: 26  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date: 5/31/2026

25. DESCRIPTION OF REQUEST
Defer project.
26. JUSTIFICATION
This is an HSIP-funded project. Right of way acquisition is underway with Arizona State Land Department and the process will not be complete in time to advertise this project in FY25. The revised HSIP Eligibility Letter is dated 02/24/2025. The request is to defer this project to the 4th quarter of FY 26. This project will be advertised with a nearby Yavapai County passing lane project also on Iron Springs Road (T044301C).
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Request Withdrawn.


PRB Meeting Date: 6/11/2024
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
6/17/2024 3:10:40 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046001R 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $75,000 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$75,000 ($75,000) (0%) $0

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226-I
$ 71 Item #:103594 (HRRR 94.3 pct ($70,725)) FY:0 FundSRC: Desc: $ -71 Item #:70124 (HRRR 94.3 pct ($70,725)) FY:2024 FundSRC:. Desc:MODERNIZATION  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Decrease budget.
26. JUSTIFICATION
Final design began March 5, 2024. Additional time is needed to develop the project and identify the necessary right of way limits. The ROW funding is programmed in FY25 in the FY25 - FY29 Program. NACOG TIP ID: HSIP 24-005R
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 11/21/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/22/2023 2:50:10 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD CONSTRUCT PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046001D 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $30,000 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$30,000 $0 (0%) $30,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226-I
$ 28 Item #:103594 (94.3pct HRRR) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project.
26. JUSTIFICATION
The project will construct an eastbound passing lane with centerline and shoulder rumble strips for safety countermeasures. This is an HRRR-funded project for Yavapai County. This subphase will be used to cover staff charges only. IGA executed October 4, 2023. Staff: $30K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 11/21/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
11/22/2023 2:50:30 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD CONSTRUCT PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046003D 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $503,000 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$503,000 $0 (0%) $503,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226-I
$ 474 Item #:103594 (94.3pct HRRR) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a new project.
26. JUSTIFICATION
The project will construct an eastbound passing lane with centerline and shoulder rumble strips for safety countermeasures. This is an HRRR-funded project for Yavapai County. This subphase will be used to cover consultant design charges only. IGA executed October 4, 2023. Consultant: $503K ($502,225.00)
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


PRB Meeting Date: 9/12/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
9/19/2023 3:32:50 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
IRON SPRINGS RD, N OF TONTO RD CONSTRUCT PASSING LANE HC1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Kingman 0000 Yavapai YYV T046001C 0.0 HSIPYYV-0(214)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $3,775,000 17. Original Program Item #: 103594
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$3,775,000 $0 (0%) $3,775,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request: 23-0009226
$ 14 Item #:103594 (100 pct HRRR) FY:0 FundSRC: Desc: $ -14 Item #:70125 (100 pct HRRR) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 25 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 1/6/2025 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Update funding sources.
26. JUSTIFICATION
This is an HSIP-funded project. This request is to update the funding sources to match the revised HSIP Eligibility Letter dated April 18, 2023. Actual amounts are as follows: 100pct HRRR $21,240.00 94.3pct HRRR $3,539,927.00 5.7pct Yavapai County Match $213,972.00
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
UPDATE FUNDING SOURCES Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation