PRB Meeting Date: 1/24/2017 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
1/27/2017 12:14:22 PM | Trent Kelso | (602) 712-6685 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
CAMELBACK RD TI | Scoping (DCR/Env Doc) | HC1O | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Phoenix | 17 | Maricopa | 204 | F011401L | 1 |
16. Original Program Budget: $0 | 17. Original Program Item #: 8887 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $2,750,000 (0%) | $2,750,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 2750 Item #:OTHR17 (MAG Tentative Program Cashflow ) FY:0 FundSRC: Desc: |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish a Scoping Project |
26. JUSTIFICATION |
During MAG and ADOT`s re-balancing efforts, this location was identified as needing capacity improvements as well as accommodating a future light rail crossing of I-17. The preferred alternative emerging from MAG�s Spine Study is to reconstruct the existing compact diamond interchange into a platform diamond interchange, with Camelback Road through-traffic and the LRT passing over the existing TI. This study will evaluate the Platform Diamond, the no-build and other viable alternatives to be determined during the initial alternatives development phase. The study will include preparation of a DCR and most-likely an Environmental Assessment. The Scoping phase (01L) and development phase are planned to be non-Federal aid funding but Construction is planned to be funded using Federal Aid. Design, R/W and Utilities are proposed in FY 2019 of the 2018-2022 ADOT tentative program and Construction in FY 2021. TIP Amendment No. DOT 17-718 will go to MAG Regional Council for approval on January 25th. Staff - $205k Consultant - $2335k ICAP - $210k |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |