2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/27/2017 12:14:22 PM Trent Kelso (602) 712-6685 205 S 17th Ave, 295, 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
CAMELBACK RD TI Scoping (DCR/Env Doc) HC1O
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 17 Maricopa 204 F011401L 1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 8887
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $2,750,000 (0%) $2,750,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 2750 Item #:OTHR17 (MAG Tentative Program Cashflow ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish a Scoping Project
26. JUSTIFICATION
During MAG and ADOT`s re-balancing efforts, this location was identified as needing capacity improvements as well as accommodating a future light rail crossing of I-17. The preferred alternative emerging from MAG�s Spine Study is to reconstruct the existing compact diamond interchange into a platform diamond interchange, with Camelback Road through-traffic and the LRT passing over the existing TI. This study will evaluate the Platform Diamond, the no-build and other viable alternatives to be determined during the initial alternatives development phase. The study will include preparation of a DCR and most-likely an Environmental Assessment. The Scoping phase (01L) and development phase are planned to be non-Federal aid funding but Construction is planned to be funded using Federal Aid. Design, R/W and Utilities are proposed in FY 2019 of the 2018-2022 ADOT tentative program and Construction in FY 2021. TIP Amendment No. DOT 17-718 will go to MAG Regional Council for approval on January 25th. Staff - $205k Consultant - $2335k ICAP - $210k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.