PRB Meeting Date: 5/23/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/25/2023 8:50:07 AM Lina Bearat (602) 538-5124 205 S 17th Ave, ,
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W JUAN ST - I-10 PAVEMENT REHABILITATION GW1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Phoenix 347 Pinal 175.7 F067301D 13.3  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103680
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $554,000 (0%) $554,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 554 Item #:70023 (100pct State) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project
26. JUSTIFICATION
This is a pavement rehabilitation project in Pinal County on SR 347 for 13.3 miles. Staff: $50k Consultant: $450k ICAP: $54k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox