PRB Actions |
| Return to previous page | View Schedule | PRB Decisions | Print this page |
| PRB Meeting Date: 3/5/2024 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 3/7/2024 1:46:05 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US 191 TI EMERGENCY RESPONSE | BRIDGE SHORING | GT1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Safford | 10 | Cochise | 331.0 | F066901X | 0.1 | 010-F(235)T |
| 16. Original Program Budget: $394,000 | 17. Original Program Item #: 103895 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $394,000 | $50,000 (0%) | $444,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 194 Item #:72223 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:0 FundSRC: Desc: | $ 50 Item #:90000 (100pct ER Funds) FY:0 FundSRC: Desc: | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 23 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 5/5/2023 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Increase budget. |
| 26. JUSTIFICATION |
| On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge was closed to traffic until a permanent repair could be made. Rental costs for temporary shoring materials and traffic control devices exceeded the original estimate. This request will provide funds to pay the final invoice for the temporary shoring materials and traffic control devices that exceeded the original estimate. The Declaration of Emergency was signed by the Arizona Governor on May 24, 2023. Contractor: $45k ICAP: $5k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 7/11/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 7/13/2023 2:04:19 PM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US 191 TI EMERGENCY RESPONSE | BRIDGE SHORING | GT1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Safford | 10 | Cochise | 331.0 | F066901X | 0.1 | 010-F(235)T |
| 16. Original Program Budget: $194,000 | 17. Original Program Item #: 103895 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $194,000 | $200,000 (0%) | $394,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 194 Item #:72223 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:0 FundSRC: Desc: | $ 200 Item #:72324 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:2024 FundSRC:. Desc:CONTINGENCY | |
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 23 | 21a. Fiscal Year: | ||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 5/5/2023 | 23a. Bid Adv Date: | ||
| 25. DESCRIPTION OF REQUEST |
| Increase budget. |
| 26. JUSTIFICATION |
| On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge is closed to traffic until a permanent repair can be made. Since the initial response, the contractor has incurred additional costs that exceed the original estimate. This request is for the on-going rent of shoring materials, traffic control devices, traffic control labor, and off-duty law enforcement. The shoring materials and traffic control devices will remain in place until the contractor is on-site for the permanent repair. The Declaration of Emergency was signed by the Arizona Governor on May 24, 2023. Contractor: $180k ICAP: $20k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Item(s) Approved. |
| PRB Meeting Date: 5/5/2023 | |||
| Request Teleconference | Teleconference Phone #: | ||
| Video Teleconference | (602) 712-7046 | ||
| 2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
| 5/15/2023 8:48:50 AM | Tricia Brown | (602) 712-7046 | 205 S 17th Ave, , 614E |
| 6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
| US 191 TI Emergency Response | Bridge Shoring | GT1Q | ||||
| 9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
| Safford | I-10 | Cochise | 331 | F066901X | 1 | |
| 16. Original Program Budget: $0 | 17. Original Program Item #: 103895 |
| Project Budget | Project Budget | Project Budget |
| 18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
| $0 | $194,000 (0%) | $194,000 |
| Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
| 19. Current Approved: | 19a. New Project/Change Request: | |
| $ 194 Item #:72223 ( ) FY:0 FundSRC: Desc: | ||
| Current Approved | New Project/Change Request | |||
| 21. Fiscal Year: | 21a. Fiscal Year: | |||
| 22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
| 23. Bid Adv Date: | 23a. Bid Adv Date: | |||
| 25. DESCRIPTION OF REQUEST |
| Establish new project. |
| 26. JUSTIFICATION |
| On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge is closed to traffic until a permanent repair can be made. This request is for an emergency procurement contract to secure the bridge structure with a temporary shoring system and installation of temporary concrete barrier on the mainline, as well as for labor, equipment, and materials provided by ADOT during the initial response. The Declaration of Emergency is pending. Contractor: $125k Staff: $50k ICAP: $19k |
| 27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
| 28. OTHER ALTERNATIVES CONSIDERED |
| REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
| Establish a New Project. | Item(s) Approved. |
| Arizona Department of Transportation |