PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 3/5/2024
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
3/7/2024 1:46:05 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
US 191 TI EMERGENCY RESPONSE BRIDGE SHORING GT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 331.0 F066901X 0.1 010-F(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $394,000 17. Original Program Item #: 103895
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$394,000 $50,000 (0%) $444,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 194 Item #:72223 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:0 FundSRC: Desc: $ 50 Item #:90000 (100pct ER Funds) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 5/5/2023 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge was closed to traffic until a permanent repair could be made. Rental costs for temporary shoring materials and traffic control devices exceeded the original estimate. This request will provide funds to pay the final invoice for the temporary shoring materials and traffic control devices that exceeded the original estimate. The Declaration of Emergency was signed by the Arizona Governor on May 24, 2023. Contractor: $45k ICAP: $5k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 7/11/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
7/13/2023 2:04:19 PM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
US 191 TI EMERGENCY RESPONSE BRIDGE SHORING GT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 10 Cochise 331.0 F066901X 0.1 010-F(235)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $194,000 17. Original Program Item #: 103895
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$194,000 $200,000 (0%) $394,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 194 Item #:72223 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:0 FundSRC: Desc: $ 200 Item #:72324 (Emergency Relief Funds - US 191 and I-10 Bridge Fire) FY:2024 FundSRC:. Desc:CONTINGENCY  

Current Approved New Project/Change Request  
21. Fiscal Year: 23 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 5/5/2023 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Increase budget.
26. JUSTIFICATION
On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge is closed to traffic until a permanent repair can be made. Since the initial response, the contractor has incurred additional costs that exceed the original estimate. This request is for the on-going rent of shoring materials, traffic control devices, traffic control labor, and off-duty law enforcement. The shoring materials and traffic control devices will remain in place until the contractor is on-site for the permanent repair. The Declaration of Emergency was signed by the Arizona Governor on May 24, 2023. Contractor: $180k ICAP: $20k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved.


PRB Meeting Date: 5/5/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/15/2023 8:48:50 AM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
US 191 TI Emergency Response Bridge Shoring GT1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford I-10 Cochise 331 F066901X 1  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103895
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $194,000 (0%) $194,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 194 Item #:72223 ( ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
On May 3, 2023, a semi-truck hit the bridge at the Interstate 10 and US 191 interchange and the overpass bridge is closed to traffic until a permanent repair can be made. This request is for an emergency procurement contract to secure the bridge structure with a temporary shoring system and installation of temporary concrete barrier on the mainline, as well as for labor, equipment, and materials provided by ADOT during the initial response. The Declaration of Emergency is pending. Contractor: $125k Staff: $50k ICAP: $19k
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation