PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 6/27/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
6/29/2023 9:33:20 AM | Derek Boland | (602) 712-6660 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
ALVERNON WAY - VALENCIA RD | CONSTRUCT SERVICE INTERCHANGE | GQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pima | 264.66 | F065801R | 2.16 |
16. Original Program Budget: $28,838,000 | 17. Original Program Item #: 101119 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$28,838,000 | $0 (0%) | $28,838,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 1632 Item #:101119 (State Match) FY:0 FundSRC: Desc: | $ -28838 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Defer ROW Subphase |
26. JUSTIFICATION |
Further development of R/W plans and additional efforts to identify parcel information are required and will take more time to complete. The team is using information identified in the Final Design Concept Report for I-10; I-19 to Kolb Rd. (H7825 01L). |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
DEFER SUBPHASE | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/25/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/19/2023 7:44:42 AM | Derek Boland | (602) 712-6660 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Alvernon Way - Valencia Rd | Construct Service Interchange | GQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pima | 264.66 | F065801R | 2.16 |
16. Original Program Budget: $29,338,000 | 17. Original Program Item #: 101119 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$29,338,000 | ($500,000) (0%) | $28,838,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 27677 Item #:101119 (NHPP FY23) FY:0 FundSRC: Desc: | $ -500 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new sub-phase |
26. JUSTIFICATION |
Funding is needed to begin R/W acquisition efforts as identified in the Final Design Concept report for the I-10: Junction Interstate I-19 to Kolb Rd. (H7825 01L). I-10 will be widened to three lanes in each direction and the service interchange at Alvernon Way will be reconstructed. Work will also include replacing I-10 overpass structures at Drexel Rd. |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
PRB Meeting Date: 4/25/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/22/2023 3:46:51 PM | Derek Boland | (602) 712-6660 | 205 S 17th Ave, 295, 614E |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
Alvernon Way - Valencia Rd | Construct Service Interchange | GQ1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Tucson | 10 | Pima | 264.66 | F065801D | 2.16 |
16. Original Program Budget: $0 | 17. Original Program Item #: 101119 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $500,000 (0%) | $500,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 500 Item #:72323 ( ) FY:2023 FundSRC:. Desc:CONTINGENCY |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project |
26. JUSTIFICATION |
Funding is needed to begin PE for the final design efforts identified in the Final Design Concept report for the I-10: Junction Interstate I-19 to Kolb Rd. (H7825 01L). |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |