PRB Actions



Return to previous page | View Schedule | PRB Decisions | Print this page


PRB Meeting Date: 12/17/2024
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
12/19/2024 12:03:59 PM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W SANTEE ST - US 70 PAVEMENT REHABILITATION GJ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 60 Gila 250.0 F064601C 2.0 060-D(227)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $14,118,000 17. Original Program Item #: 103679
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$14,118,000 ($6,968,000) (0%) $7,150,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 13313 Item #:103679 ( STBGP 94.3pct ($13,313,114)) FY:0 FundSRC: Desc: $ -13313 Item #:72526 (STBGP 94.3pct ($13,313,114)) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 26 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 2/28/2025 24. Verified all of the new funding sources
23. Bid Adv Date: 8/1/2025 23a. Bid Adv Date: 3/31/2025

25. DESCRIPTION OF REQUEST
Advance project from FY26 to FY25. Decrease Construction Funding.
26. JUSTIFICATION
Capacity exists to advance the project from FY26 to FY25. The initial project scope included removing and replacing all sidewalks. The project will only remove and replace sidewalk that is heaved, cracked or no longer ADA compliant, rather than all sidewalks. ICAP is included in the cost estimate.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/25/2023
Request Teleconference Teleconference Phone #:
Video Teleconference

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
5/3/2023 8:33:32 AM Rehnuma Rahman (602) 712-7342 205 S 17th Ave, Next, O68R
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
W SANTEE ST - US 70 PAVEMENT REHABILITATION GJ1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Safford 60 Gila 250.0 F064601D 2.0 060-D(227)T
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103679
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $416,000 (0%) $416,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 416 Item #:70023 (State 100pct ) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish new project.
26. JUSTIFICATION
The project is pavement rehabilitation. The survey and pavement design will be performed by ADOT staff. The design will be performed by a design consultant. Staff: $126K Consultant: $250K ICAP: $40K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox

Arizona Department of Transportation