PRB Actions |
Return to previous page | View Schedule | PRB Decisions | Print this page |
PRB Meeting Date: 12/19/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
12/22/2023 10:05:22 AM | Rehnuma Rahman | (602) 712-7342 | 205 S 17th Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
REAY LN - 8TH ST | PAVEMENT REHABILITATION | GI1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 70 | Graham | 335.0 | F064701D | 5.0 | 070-A(225)T |
16. Original Program Budget: $461,000 | 17. Original Program Item #: 103723 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$461,000 | $44,000 (0%) | $505,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 461 Item #:70023 ( ) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT | $ 44 Item #:70024 (100pct State ) FY:2024 FundSRC:. Desc:ENGINEERING SUPPORT |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Increase budget. |
26. JUSTIFICATION |
Funding is needed for additional survey efforts beyond what was originally identified to be needed. Additionally, funding is needed to conduct Class III cultural surveys in accordance with SHPO / NEPA requirements, which were also originally not known to be needed. Consultant: $39K ICAP: $5K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Item(s) Approved. |
PRB Meeting Date: 4/25/2023 | |||
Request Teleconference | Teleconference Phone #: | ||
Video Teleconference | |||
2. Form Date: | 3. Project Manager/Presenter: | 4. Phone Number(s): | 5. Mail Drop: |
5/17/2023 7:51:53 AM | Rehnuma Rahman | (602) 712-7342 | 205 S 17th Ave, Next, O68R |
6. Project Name/Location: | 7. Type of Work: | 8. CPS Id: | ||||
REAY LN - 8TH ST | PAVEMENT REHABILITATION | GI1Q | ||||
9. District: | 10. Route: | 11. County: | 12. Beg. MP: | 13. TRACS #: | 14. Len. (mi): | 15. Fed ID#: |
Safford | 70 | Graham | 335.0 | F064701D | 5.0 | 070-A(225)T |
16. Original Program Budget: $0 | 17. Original Program Item #: 103723 |
Project Budget | Project Budget | Project Budget |
18. Current Approved: | 18a. New Project/Change Request: | 18b. Final: |
$0 | $461,000 (0%) | $461,000 |
Funding Source(s) | Funding Source(s) | 20. JPA #, Signed, Adot Adv.: |
19. Current Approved: | 19a. New Project/Change Request: | |
$ 461 Item #:70023 (State 100pct ) FY:2023 FundSRC:. Desc:ENGINEERING SUPPORT |
Current Approved | New Project/Change Request | |||
21. Fiscal Year: | 21a. Fiscal Year: | |||
22. Bid Pkg Rdy Date: | 22a. Bid Pkg Rdy Date: | 24. Verified all of the new funding sources | ||
23. Bid Adv Date: | 23a. Bid Adv Date: |
25. DESCRIPTION OF REQUEST |
Establish new project. |
26. JUSTIFICATION |
The project is pavement rehabilitation. The survey and pavement design will be completed by ADOT staff. The design will be performed by a consultant. Staff: $117K Consultant: $300K ICAP: $44K |
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST |
28. OTHER ALTERNATIVES CONSIDERED |
REQUESTED ACTIONS | APPROVED/RECOMMENDED ACTIONS |
Establish a New Project. | Item(s) Approved. Subject to PPAC Approval. |
Arizona Department of Transportation |