PRB Meeting Date: 1/28/2025
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
1/30/2025 9:47:13 AM Tricia Brown (602) 712-7046 205 S 17TH AVE, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
NW OF BOUSE - SE OF BOUSE PAVEMENT REHABILITATION GF1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 72 La Paz 20.4 F063901C 10.0  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $8,503,000 17. Original Program Item #: 103685
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$8,503,000 $3,600,000 (0%) $12,103,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 8503 Item #:103685 ( ) FY:0 FundSRC: Desc: $ -8503 Item #:72527 (.) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 27 21a. Fiscal Year: 25  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 3/21/2025 23a. Bid Adv Date: 4/30/2025

25. DESCRIPTION OF REQUEST
Increase budget; change project schedule
26. JUSTIFICATION
This pavement rehabilitation project will mill and replace 3 inches of asphaltic concrete and chip seal on approximately 9.5 miles of State Route 72 in the Bouse area. The pavement rehabilitation includes both the travel lanes and shoulders. The request includes the difference in the estimated construction cost presented in the 09/05/2022 Project Level Scoping document of $11.4M and the programmed amount. The project was inadvertently programmed at $8.5M. Additional funds are needed due to the increase in unit costs for concrete ford walls, mobilization, and cattleguards. The request is also to advance the project from FY 27 to 4Q FY 25. ICAP is included in this request.
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Change in FY. Change in Schedule. Item(s) Approved. Subject to PPAC Approval.


PRB Meeting Date: 4/25/2023
Request Teleconference Teleconference Phone #:
Video Teleconference (602) 712-7046

GENERAL INFORMATION
2. Form Date: 3. Project Manager/Presenter: 4. Phone Number(s): 5. Mail Drop:
4/27/2023 11:27:41 AM Tricia Brown (602) 712-7046 205 S 17th Ave, , 614E
PROJECT INFORMATION
6. Project Name/Location: 7. Type of Work: 8. CPS Id:
NW OF BOUSE - SE OF BOUSE PAVEMENT REHABILITATION GF1Q
9. District: 10. Route: 11. County: 12. Beg. MP: 13. TRACS #: 14. Len. (mi): 15. Fed ID#:
Yuma 72 La Paz 20.44 F063901D 10  
PROJECT REQUEST SUMMARY
16. Original Program Budget: $0 17. Original Program Item #: 103685
Project Budget Project Budget Project Budget
18. Current Approved: 18a. New Project/Change Request: 18b. Final:
$0 $390,000 (0%) $390,000

Funding Source(s) Funding Source(s) 20. JPA #, Signed, Adot Adv.:
19. Current Approved: 19a. New Project/Change Request:
$ 390 Item #:79023 (State 100pct ) FY:0 FundSRC: Desc:  

Current Approved New Project/Change Request  
21. Fiscal Year: 21a. Fiscal Year:  
22. Bid Pkg Rdy Date: 22a. Bid Pkg Rdy Date: 24. Verified all of the new funding sources
23. Bid Adv Date: 23a. Bid Adv Date:

25. DESCRIPTION OF REQUEST
Establish design project.
26. JUSTIFICATION
The pre-scoping document completed in September 2022 identifies full-width 3" mill and 3" AC replacement with chip seal. Additional scope items include tree removal, seeding, right of way fence replacement, shoulder build-up, and replacement of cattle guards. Construction for this project currently shown in FY27 in the Tentative FY24 - FY28 Five Year Program . Staff: $50K Consultant: $303K ICAP:$37K
27. CONCERNS OF THE PROJECT TEAM REGARDING THE REQUEST

28. OTHER ALTERNATIVES CONSIDERED


REQUESTED ACTIONS APPROVED/RECOMMENDED ACTIONS
Establish a New Project. Item(s) Approved. Subject to PPAC Approval.


For Project Resource Office information or questions: PRO Mailbox